What Does a Kitchen Remodel Cost in South Florida?

Why a kitchen has no honest price per square foot, and the layout, code, hurricane, permit, tax and contract decisions that actually set a South Florida kitchen budget.

220-amp appliance circuits, at minimum
24 inmaximum reach to a counter outlet
400 cfmhood size where makeup air rules start
By Elbaz ConstructionUpdated September 26, 202610 min readSources: Florida Building Code · NEC 2020 · Florida Statutes · FEMA · Florida DOR

Kitchen remodel cost

The short answer

A kitchen remodel in South Florida has no honest price per square foot, and a “10 by 10 kitchen” figure tells you little. What sets the budget is whether the layout stays or moves (which decides how much of the building code applies), the electrical and ventilation work the current code requires once circuits and the hood are touched, hurricane-rated openings if a window or slider is replaced in Miami-Dade or Broward, and the cabinets, stone and appliances you choose. Permit fees, sales tax and design come on top. For scale only: a national survey put the average midrange minor kitchen remodel at $28,458 in 2025.

Layout

Same footprint, or moved sink, range and walls: the single biggest fork in the budget.

Code upgrades

Changed circuits, counter outlets and a new hood bring in today’s electrical and exhaust rules.

Hurricane code

A replaced window or slider must be impact-rated or protected in Miami-Dade and Broward.

Paperwork

Permits, fees, sales tax and the contract’s dollar lines.

Scope and code

The first fork: keep the layout, or move it

Florida classifies work on an existing house by what it changes, in the Florida Building Code, Existing Building (8th edition, 2023). Replacing cabinets, counters and fixtures with new ones that serve the same purpose is a Level 1 alteration (section 602.1). Reconfiguring the space, adding or removing a door or window, or extending a system is Level 2 (603.1), and it brings more of the current code into the job. In a kitchen, three decisions push a project from one to the other:

Deep teal shaker kitchen remodel with white quartz counters, brushed-gold hardware and a marble hexagon backsplash, by Elbaz ConstructionSame footprint

Keep the layout

Cabinets, counters and appliances are replaced where they are. The plumbing and gas stay put; the budget goes into what you see.

Photo: a teal shaker range wall with a stainless hood and a pro-style range.

Marble island with an undermount sink, brass tapware and open circulation on both sidesNew island sink

Move the sink or range

A sink moved to an island needs new drain and vent piping under the floor; a range moved needs new gas or a new circuit, and the hood duct follows it.

Photo: an island with an undermount sink facing a gas rangetop under a stainless hood.

Close view of the mitred slab edge and undermount sink on the islandOpen plan

Take out a wall

Opening the kitchen to the living area is structural work if the wall carries load: an engineer’s design, a beam and a structural permit.

Photo: an open kitchen with a stone island, handleless cabinets and double wall ovens.

None of this is a reason not to change the layout; a better kitchen is often a moved one. It is a reason to decide the layout first, before cabinets and finishes, because the layout decides the trades, the permits and the engineering, and those are fixed costs that finishes cannot offset.

Code upgrades

Behind the walls: the electrical and ventilation code

The Florida Building Code adopts the 2020 National Electrical Code (section 2701.1). An older kitchen rarely meets it, and once the circuits are changed the new work has to. The rules that most often add work in a kitchen remodel:

  • Countertop receptacles need GFCI protection (NEC 210.8(A)(6)), and they must be spaced so that no point along the counter wall is more than 24 inches from one (210.52(C)(1)). A longer or reshaped counter means more outlets.
  • At least two 20-amp small-appliance circuits serve the kitchen receptacles (210.11(C)(1)). Many older kitchens have fewer, which is why a remodel often means new circuits back to the panel, and sometimes a panel with room for them.
  • AFCI protection: when a kitchen branch circuit is modified, replaced or extended, it must be AFCI-protected (210.12(D)), apart from a short extension of 6 feet or less that adds no outlets.
  • Lighting: new permanently installed fixtures must meet the efficacy minimums of the Florida Energy Code (R404.1), which applies to new lighting that is part of an alteration (R503.1.4).
Where the building and electrical codes touch a kitchen remodelA kitchen elevation with six numbered points: 1, a range hood discharges outdoors through a duct, and large hoods can require makeup air; 2, countertop receptacles need GFCI protection and no point along the counter may be more than 24 inches from one; 3, at least two 20-amp small-appliance circuits; 4, branch circuits that are modified, replaced or extended need AFCI protection; 5, a window or sliding door replaced in Miami-Dade or Broward must be impact-rated or protected; 6, moving the sink means new drain and vent piping and a plumbing permit.1234561Range hoodDucted outdoors; big hoods need makeup air2Counter outletsGFCI; none over 24 in away3Appliance circuitsTwo or more 20-amp circuits4Changed circuitsAFCI protection5Window or sliderImpact-rated in the HVHZ6Moved sinkNew drain and vent; plumbing permitSix places the codes touch a kitchen remodel1234561Range hoodDucted outdoors; big hoods need makeup air2Counter outletsGFCI; none over 24 in away3Appliance circuitsTwo or more 20-amp circuits4Changed circuitsAFCI protection5Window or sliderImpact-rated in the HVHZ6Moved sinkNew drain and vent; plumbing permit
Simplified. Sources: 2020 National Electrical Code 210.8, 210.11, 210.12 and 210.52 (adopted by the Florida Building Code, 8th edition); Florida Building Code, Residential M1503.1 and M1503.4; Florida Building Code, Building 1626.1. Your electrician, mechanical contractor and building official apply them to your kitchen.

The hood is the other code line item. The Florida Residential Code requires range hoods to discharge to the outdoors through a duct (M1503.1; ductless hoods are allowed by exception), so a hood on an interior wall or island needs a duct route through the ceiling or roof. Big hoods add a second requirement: an exhaust system able to move more than 400 cubic feet per minute must have makeup air (M1503.4). Florida’s version exempts single-family homes up to 400 cfm, and up to 800 cfm when there are no gravity-vent appliances inside the conditioned space. A professional-style range with a large hood can pass those lines, and makeup air means a powered or passive air supply with its own ductwork and controls. Choose the range and hood with that in mind, not after.

Cooking wall with a stainless range, wall-mounted hood and marble splashback between tall cabinetry
A range alcove from an Elbaz Construction kitchen remodel: a stainless hood over a gas rangetop, a pot filler and large-format wall tile.

South Florida rules

Windows, flood zones and condos: the local multipliers

Windows and sliders. Miami-Dade and Broward are the High-Velocity Hurricane Zone. There, glazing and exterior doors “shall meet impact test criteria or be protected with an external protection device” (section 1626.1). If the kitchen remodel replaces the window over the sink or the slider to the patio, that opening becomes an approved impact product with its own permit documents. Palm Beach County is outside the HVHZ, so its requirements differ. See our hurricane-rated window systems.

Flood zones. In a Special Flood Hazard Area, improvements costing 50% or more of the structure’s market value trigger full flood compliance. A kitchen alone rarely reaches that line, but a kitchen that is part of a larger remodel can, and the kitchen line items count differently: FEMA’s desk reference counts built-in appliances, cabinets and finishes in the cost, but leaves out plug-in appliances. Our FEMA 50% rule guide explains the test.

Condos. In a condominium the association’s rules come before the building department: what you may change, when work can be done, and what the association must approve first. Our condo renovation guide walks through the approvals and permits.

Open-plan grey shaker kitchen remodel with granite counters, an island cooktop and stainless apron sink, by Elbaz Construction
An island with a gas cooktop under a stainless island hood whose chimney rises to the ceiling, from an Elbaz Construction kitchen remodel.

Finishes

Cabinets, stone and appliances: where the choices are yours

Once the layout and the code work are fixed, the rest of the budget is choice. Cabinet construction and finish, the counter material and how many slab edges and cut-outs it needs, and the appliance package set the remaining spread, and they are the one part of the budget you can tune line by line without touching the permit. Two practical points: a panel-ready refrigerator or wall ovens need a tall cabinet built around their exact specifications, so appliances are chosen before the cabinets are drawn; and a stone island with a waterfall end or a sink cut-out is priced from the slabs it needs, so its size is best settled on the drawings.

Tall cabinetry housing built-in ovens beside a wide drawer bank with brass hardware
A gas rangetop and drawer base beside panel-fronted tall cabinetry, from an Elbaz Construction kitchen remodel.
Deep teal shaker kitchen remodel with white quartz counters, brushed-gold hardware and a marble hexagon backsplash, by Elbaz Construction
A built-in refrigerator and a wall oven set into teal shaker tall cabinets, from an Elbaz Construction kitchen remodel.

For scale, the one independent benchmark we cite: in Zonda’s 2025 Cost vs Value Report, the national average job cost of a midrange minor kitchen remodel was $28,458, with an estimated resale value of $32,141. That project keeps the layout and replaces fronts, counters, sink and appliances. It is a national average, not a South Florida quote and not an Elbaz price.

The rest of the budget

Permits, fees and sales tax

Permits. A kitchen that moves plumbing, adds circuits, changes gas or removes a wall needs permits for that work. Florida’s HB 803 (in force since July 1, 2026) lets the owner of a single-family home ask for an exemption for small jobs, but it excludes all electrical, plumbing, structural, mechanical and gas work and homes in a flood hazard area, so it does not cover a real kitchen remodel. The same law set review clocks (section 553.792): 5 business days for listed permits under $15,000 on an existing single-family home, and 30 business days for most other home permits. Our three-county permit guide shows which office handles your address.

Fees are set by each building department. As one published example, unincorporated Miami-Dade County charges 50 cents per square foot of the whole structure for alterations to a single-family home, with a minimum of $147 and a maximum of $847.95 before surcharges (Implementing Order 4-63); plumbing and electrical permits are separate. Cities publish their own schedules.

Sales tax is inside the contract price: Florida treats contractors as the consumers of the materials they install (Rule 12A-1.051), so cabinets, stone and fixtures carry the state rate plus the county surtax.

Contracts and payments

The contract: three Florida rules that protect a kitchen budget

  1. ContractRecovery Fund noticeResidential contracts over $2,500 must include the notice about the Florida Homeowners’ Construction Recovery Fund (section 489.1425).
  2. DepositOver 10% starts two clocksIf the first payment is more than 10% of the contract price, the contractor must apply for the permits within 30 days and start work within 90 days after they are issued, unless there is just cause or a written agreement (section 489.126).
  3. Before inspectionNotice of commencementWhen the direct contract is greater than $5,000, a recorded notice of commencement must be filed before the first inspection (section 713.135). A full kitchen remodel is almost always over that line.
  4. OrderingLong-lead itemsCabinets, stone and appliances are ordered against approved drawings. Tie each payment to delivered or inspected work, and put every change in writing with its price and schedule effect before it is built.
Bathroom stripped back during demolition, with the wall board removed, supply pipework exposed and debris still on the floor
Demolition on an Elbaz Construction remodel: wallboard stripped to expose the supply pipes. What demolition shows is priced and approved before work continues.

Interactive checklist

Before you set a kitchen budget: a checklist

0 of 8 done

Our process

How we price a kitchen remodel

We price a kitchen remodel from the room and the house, not from a size: we look at the layout you want, the walls, the panel, the plumbing and gas routes, the hood path and any window or slider, then settle the layout and design with you before the finishes. On a design-build project, the drawings the building department reviews are the drawings we price. If the kitchen is part of a larger project, our guide to whole-house remodel costs covers the rest of the house.

For an example of a full kitchen scope, with shaker cabinetry, a professional range and built-in refrigeration, see our emerald shaker kitchen remodel. Send us photos or a plan of your kitchen and we will tell you which of these rules apply before we talk about numbers.

Our work

Kitchens we have built

Real Elbaz Construction projects. Photos show the work only; none is presented as a particular home or location. Tap a photo to enlarge.

Google reviews

What clients said on Google.

4.8348 Google reviews (checked Sep 2026)

Asher was the best choice I have made. We love the outcome of the ADU . They showed up on time and did a great job, were friendly. No issues at all during the whole process. Very organized team . I would recommend them to everyone I know !

Robert Bryan

Great experience! The team was professional, efficient, and delivered high-quality work on time. They communicated clearly throughout the project and exceeded our expectations. Highly recommend for any construction needs!

Andrew

If you are planning to remodel your kitchen or bathroom or do any other construction project, call Sean from Elbaz Construction . He has a lot of experience and will recommend the best options/ suggestions to your project. He did high quality job !

Kameron Allison

Thank you Ashley ! We love the new bathrooms. Good with communication and very clear with explanations . I will definitely use them again in the future

Andrew Tyupa

Asher has a lot of experience . We replaced our windows to energy efficient windows. He got down to business right away and did high quality work. His team is very professional! Thanks again

jessica berliner

I give them a five star rating not only for their excellent roofing skills and timelines, but also for their competitive pricing and the honesty and professionalism of the team !! We are very pleased with the outcome

Zachary Gugliotta

Genuine Google reviews of Elbaz Construction, reproduced as written. They describe general work with us, not the specific topic of this article. Read all reviews on Google.

Questions

Quick answers on kitchen budgets

Rules vary by address and scope. For your property, call 754-236-0675.

There is no reliable per-square-foot figure. The budget depends on whether the layout stays or moves, the electrical and ventilation work the current code requires, any hurricane-rated window or door, and the cabinets, stone and appliances chosen. For scale only, the 2025 Cost vs Value Report put the national average for a midrange minor kitchen remodel at $28,458. We price each kitchen after seeing it.

A size alone does not set the price. Two 10-by-10 kitchens can differ widely depending on whether the sink or range moves, whether a wall comes out, how many new circuits the electrical code requires, and the finishes. Decide the layout first; then the price can be set.

Usually, yes. Moving a sink needs new drain and vent piping and a plumbing permit; moving a range needs new gas or a new circuit, and the hood duct follows it. Under the Florida Building Code, Existing Building, reconfiguring the space is a Level 2 alteration, which brings more of the current code into the project.

Range hoods must discharge outdoors through a duct (Florida Residential Code M1503.1, with an exception for ductless hoods). Hoods able to exhaust more than 400 cfm need makeup air under M1503.4, but Florida exempts single-family homes up to 800 cfm when no gravity-vent appliances are inside the conditioned space.

In most cases, yes: moving or adding plumbing, electrical, gas or structural work needs permits. Florida's 2026 HB 803 owner exemption for small jobs excludes all electrical, plumbing, structural, mechanical and gas work, so it does not cover a typical kitchen remodel.

Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Sources

Where these facts come from

  1. Florida Building Code, Existing Building, 8th edition (2023): classification of work — sections 602.1, 603.1
  2. Florida Building Code, Building, 8th edition (2023), chapter 27: adoption of NFPA 70 (2020) — section 2701.1
  3. 2020 National Electrical Code 210.52(C): countertop receptacles (commentary with the code text)
  4. 2020 National Electrical Code 210.12(D): AFCI where branch circuits are modified, replaced or extended
  5. Florida Building Code, Residential, 8th edition (2023), chapter 15: exhaust systems — M1503.1, M1503.4
  6. Florida Building Code, Energy Conservation, 8th edition (2023): residential lighting — R404.1
  7. Florida Building Code, Energy Conservation, 8th edition (2023): alterations — R503.1.4
  8. Florida Building Code, Building, section 1626.1 (HVHZ impact criteria)
  9. FEMA P-758, Substantial Improvement/Substantial Damage Desk Reference — sections 4.4.1, 4.4.2
  10. Florida Senate: HB 803 (2026) bill summary
  11. Section 553.792, Florida Statutes: permit application deadlines
  12. Miami-Dade County Implementing Order 4-63: building fee schedule — section I.B.3
  13. Rule 12A-1.051, Florida Administrative Code: contractors as consumers of materials — (2)(a)
  14. Florida Department of Revenue, DR-15DSS: discretionary sales surtax rates, 2026
  15. Sections 489.126, 489.1425 and 713.135, Florida Statutes: deposits, the Recovery Fund notice, the notice of commencement
  16. Zonda, 2025 Cost vs Value Report (national averages). © 2025 Zonda Media; full data at costvsvalue.com — Minor Kitchen Remodel, midrange

General information about the Florida Building Code, the National Electrical Code as adopted in Florida, Florida statutes and published fees as of September 2026, not legal, tax or financial advice. Your building department, the permits issued and your contract decide how they apply to your kitchen. No figure on this page is an Elbaz Construction price.

Planning a kitchen remodel?

Settle the layout before the numbers

We plan kitchen remodels across Miami-Dade, Broward and Palm Beach with the layout, the code work and the permit package settled first.