Most owners think of a building permit as a piece of paper you obtain and then hold. Doral publishes it as something closer to a lease: it runs for a fixed period, and only one specific event renews it.
The City states that permits "expire and become null and void if work is not started and an inspection is approved within 180 days from the issuance date of the permit", and that once work has commenced "the permit will expire when work is suspended or abandoned for a period of 6 months, unless an approved inspection is obtained". Read those two sentences together and the rule is simple and unforgiving: an APPROVED INSPECTION is the only thing that resets the clock. Not paying a fee, not ordering materials, not having a crew on site. On a project that pauses for a kitchen delivery, a family holiday or a change of mind, that is the difference between a live permit and a dead one.
From issuance, to work started AND an inspection approved. The City states a permit that misses it is null and void.
After work commences, the permit expires if work is suspended or abandoned for six months unless an approved inspection is obtained in that window.
The City states work done without a permit "is subject to double permit fees and may have to be partially or completely demolished".
Elbaz Construction is a licensed general contractor working across Miami-Dade. In Doral the pattern is a city of relatively young housing — much of it built from the 1990s onward — where the work is rarely structural rescue and usually a considered upgrade inside an existing footprint.
The commonest Doral project and the one where the inspection calendar matters most, because electrical, plumbing and mechanical each have to be signed off before anything closes up.
Small rooms, several trades, and a waterproofing inspection that has to happen before a single tile goes on.
One permit record, one sequence of inspections, and one accountable contractor rather than a queue of trades arriving in the wrong order.
An addition changes lot coverage and setbacks before it changes anything else, so it starts as a zoning question and becomes a construction one later.
Miami-Dade is HVHZ. Every unit carries a product approval and an anchorage detail, and both are reviewed rather than assumed.
Level, substrate and threshold decisions are made once, at the beginning, and they are visible for the life of the floor.
Two approvals rather than one: the association’s and the City’s, and the association’s usually comes first.
Structures outside the house are permitted construction with footings and electrical work, not landscaping.
Common here precisely because of the 180-day rule. It is workable, and it is far cheaper addressed before a new application than during one.
South Florida projects by Elbaz Construction
Both sets are Elbaz Construction projects in South Florida. Neither is represented as being in Doral, and neither is presented as the same property as the other.




The waterfall end and the overhang that carries the stools are set out before the worktop is templated. Move either afterwards and the whole slab is re-cut.
An island with a sink and a hob has waste, water and power reaching it under the slab. That is first-fix work with its own inspection, done long before anything looks like a kitchen.
Where the sink run sits under glazing, the finish reads differently at every hour. It is why worktop and cabinet colours are chosen in the room rather than from a sample board on a desk.
Handles, tap, stools and pendants all arrive at the end. Until they do, a finished kitchen looks unfinished — and then it does not.

The things that go wrong on Doral projects are rarely craft problems. They are sequencing problems, and almost all of them trace back to the same published rules.
A project planned so that an inspection lands inside every window never meets the 180-day rule or the six-month rule at all.
The City states that where there is a master permit and multiple sub-permits, each must have an approved final inspection to be considered closed.
Inspections must be requested by 4pm and are performed the following business day, so readiness is a decision made the afternoon before.
Miami-Dade glazing and doors carry approvals for the zone. A late substitution is a revision, not a swap.
The City publishes both consequences. Finding inherited unpermitted work before a new application is far cheaper than during one.
A closed record is what a future buyer’s search finds, and what an association or an insurer asks for.
Everything above is Doral-specific or Miami-Dade-specific. The wind zone, the water table and the wet season apply across South Florida and are planned for on every project we run.

The second set is a different property and a different room. It is here because a bathroom is where the invisible half of a remodel is easiest to explain: almost everything that gets inspected disappears behind tile.

The lit niche, framed into the large-format wall tile

The linear drain where the mosaic floor meets the wall

Fan-shaped mosaic turning the corner of the shower floor

The walk-in shower behind its sliding glass screen

The vanity, matt black tap and backlit mirror cabinet

Not an exhaustive list — the six decisions where this county and this climate change the answer.
The photographs on this page are Elbaz Construction projects in South Florida. None is represented as having been taken in Doral.
What the work is, and what is already on record against the property. On a Doral remodel the second question matters as much as the first, because an inherited open permit surfaces the moment a new application touches the same system.
What is actually there: structure, services, levels and anything a previous owner left behind. Assumptions are cheap until an inspector disagrees with one.
A set built to the City’s requirements, with drawing files named to Miami-Dade County’s naming conventions, which Doral states it follows.
Glazing, doors and anything else with an approval number selected with its documentation attached — in the HVHZ that paperwork is part of the review.
The application is lodged through the City’s CSS portal, complete rather than nearly complete. The City’s stated goal is ten business days, and it calls it a goal.
Comments answered as a set. A partial response starts another cycle on a property whose clock is already running.
Before a tool is lifted, the programme names when each inspection will be called, so no window in the 180-day or six-month rule is ever left empty.
Requested by 4pm for the following business day, and called only when the work will genuinely pass.
Master and sub-permits each taken to an approved final, because the City states each must have one to be considered closed.
Every statement above is the City of Doral’s published position as read on 19 August 2026 at cityofdoral.com. Municipal procedure changes; confirm the current requirement with the Building Department before relying on any of it. No fee is quoted here — the City publishes a fee schedule and a fee estimator, and both are the City’s to state.
Five steps. The first and the last are the ones owners underestimate, and on a Doral property they are the two that decide whether the clock is ever a problem.
What the City already holds against the address, including anything open or expired from a previous owner. This is a search, and it costs nothing but time.
Whether the work stays inside the existing footprint, and which trades it touches. That list becomes the inspection calendar.
Drawings assembled to the City’s requirements, with files named to the Miami-Dade conventions Doral follows, and product approvals attached.
The application, the documents and the fees run through the City’s portal. Permit status and inspection requests live in the same account afterwards.
Every inspection requested by 4pm the day before, every window in the 180-day and six-month rules filled, and every master and sub-permit taken to an approved final.
We do not publish prices, and we do not publish the City’s fees or timelines as if they were ours to promise. What follows is where the number and the calendar actually move.
Twenty minutes on the phone, or at the property, answers most of it. We will look up what the City holds against the address while we talk, tell you plainly what the record shows, and be clear about which questions only the Building Department can answer.

Doral questions
The City states that permits "expire and become null and void if work is not started and an inspection is approved within 180 days from the issuance date of the permit". After work has commenced, a permit expires if work is suspended or abandoned for six months "unless an approved inspection is obtained". An approved inspection is what resets it.
An approved inspection, and nothing else. Not paying, not ordering materials, not having a crew on site. That is the single most useful thing to know about running a project here, and it is why our programme names when each inspection will be called before any work starts.
It becomes null and void, and the City is explicit that an expired permit affects the property. Renewing or re-permitting is possible — the City publishes a Renewal of Expired Permits route — and it is a conversation to have with the Building Department rather than a form to guess at.
"Inspections must be requested by 4pm", and they are "performed the following business day". The City also invites you to call between 7:00am and 8:00am to speak with your inspector about the day’s route.
When every one of them has an approved final. The City states that "each master and sub-permit must have an approved final inspection in order to be considered closed", which is the step most often left half-done.
The City states such work "is subject to double permit fees and may have to be partially or completely demolished", and that "the transfer of property could be delayed when non-permitted work is discovered". It is workable, and it is much better found before a new application than during one.
The City allows it where you meet the owner/builder exemption and complete the Owner/Builder Affidavit, and warns that you then "take all the responsibilities and liabilities as a contractor". Its own experience, published on the same page, is that owner-builders manage on small jobs more often than on large ones.
The City says processing "depends mainly on the amount of work in the system" and that "department goals aim for 10 business days or as required by state statute". That is a goal the City has stated, not a promise anyone can make on its behalf.
The City states that generally new construction, commercial alterations and changes of occupancy require one, and that "if you are a homeowner doing repair work on your home you do not need a CO". For your specific scope the Building Department is the authority.
Yes. We assemble the submittal, file it through CSS, answer the review, book every inspection by the cut-off and take every master and sub-permit to an approved final. What we will not do is promise a review duration that is the City’s to decide.
Licence CBC1265280 — licensed, bonded and insured, so several permitted scopes on one property run under a single contract.
Before a tool is lifted, the programme says when each inspection will be called. That is what stops the 180-day and six-month rules from ever becoming a problem.
An inherited open or expired permit surfaces the moment a new application touches the same system. Better found in week one.
A failed call on a next-business-day system costs more than the day it takes.
The City is explicit that each one needs its own approved final. A project is not finished when it looks finished.
Fees, review durations and whether a specific address has an open permit belong to the Building Department. We will tell you exactly who to ask and we will ask with you.
Financing options are available — ask and we will explain what applies to your project.
A closed permit record and the documents to prove it, which is what a future buyer’s search will find.
Reproduced verbatim from our Google Business Profile. Nothing here has been edited, merged or rewritten.
Redid my whole bathroom and kitchen. Great service - Great quality - very quick - very professional !! Highly recommended!
Adir DavidovGoogle reviewThey are amazing! Very professional. Met my exact requests with so much patience and knowledge. They renovated my whole house and the whole process was such a breeze. I highly recommend them!
Lee MoraliGoogle reviewWe hired them to renovate our investment property and they provided exceptional quality service for an affordable price!
Shir PartushGoogle reviewAmazing experience with the entire company! They did a great job in my house for some work that needed to be completed, and I am extremely happy with the result. Super professional & great service. I highly recommend Elbaz Construction.
Mia ZafraniGoogle reviewAfter I've been Looking for a good company to renovate my house , I found those guys! These people are super professional super honest super Fast !! Don't hesitate to Rent their service! They are number one!!
carmit cohenGoogle reviewI highly recommend them for home improvement. They renovated my master bathroom and a few upgrades for other guest bathrooms. They are very professional, courteous and transparent. They are great at communicating and finding ways to streamline the work. Sean has impeccable project management and customer relationship management skills. Very pleased with the work!
Omri BGoogle reviewProudly serving homeowners across Miami-Dade, Broward and Palm Beach
104 municipalities across three counties — and we hold the licence to build in all of them. Not sure about your address? Ask us.
Send the property address and roughly what you have in mind. We will check what is on record, sketch the inspection calendar your scope implies, and tell you where the real constraints are before anyone talks about a price.
Licensed, bonded and insured — certified building contractor CBC1265280. Serving Miami-Dade, Broward and Palm Beach.
We have your details and a member of the team will be in touch. If it is urgent, call 754-236-0675.