Single-storey stucco ADU with a black steel entry canopy, black door, shuttered window and a paver patio
Project 02: the entry elevation. Its own front door, its own patio — the difference between an accessory dwelling and a back room.

The service

There is no statewide
right to build one.

Florida Statutes section 163.31771 permits local governments to allow accessory dwelling units. It does not require them to. Bills that would have created a statewide requirement — CS/CS/SB 48 and its House companion CS/HB 313 — did not become law; the House companion died in subcommittee on 13 March 2026.

So the answer is local, and it varies considerably. Miami-Dade County adopted its own accessory dwelling unit ordinance in 2022 under County Code section 33-22, applying inside the Urban Development Boundary in specified zoning districts, with minimum lot sizes and a lower threshold for garage conversions than for new detached units. Broward and Palm Beach municipalities each set their own rules.

  • Zoning decides first

    District, lot size, setbacks and coverage determine whether a unit is possible at all.

  • Local, not statewide

    What your municipality permits is the only answer that matters.

  • Feasibility before design

    Establishing the constraints first is what stops a design being drawn twice.

Talk through your parcel

Scope

What the permitting service covers

From an address to an approved permit, with the feasibility question answered honestly at the start.

A variance is a different process

If the parcel misses a dimensional requirement, a variance or administrative adjustment may be possible — but it is a discretionary public process with its own timetable and no guaranteed outcome. It is worth knowing that at feasibility rather than after drawings exist.

01

Feasibility

  • Zoning district, permitted use and whether an accessory unit is allowed
  • Minimum lot size, setbacks, separation and height limits
  • Lot coverage, floor area and parking requirements
  • Whether the parcel sits inside any applicable development boundary
02

Constraints and services

  • Utility capacity and whether separate connections or meters are required
  • Septic or sewer capacity where applicable
  • Flood mapping and required finished floor elevation
  • Easements, association restrictions and deed limitations
03

Documentation

  • Survey coordination where a current one does not exist
  • Site plan showing setbacks, coverage, parking and separation
  • Construction drawings for the proposed unit
  • Engineering coordination where structure or new construction requires it
04

Submission and review

  • Zoning review and any variance or administrative adjustment application
  • Building permit submission to the authority having jurisdiction
  • Correction responses handled by us rather than passed to you
  • Coordination of utility and, where relevant, environmental applications
Compact ADU kitchen with wood-grain slab cabinet fronts, white subway tile, open timber shelving on black brackets and a stainless range
Project 01: a full kitchen on one wall — plumbing and ventilation kept in one place, which is what makes a compact plan work.

Stills from the two completed units on this page. They illustrate the stages; they are not photographs of the stage named beside them.

How it runs

Six stages,
feasibility first

The order matters: nothing should be drawn until the parcel has been checked.

  1. 01

    Address and zoning check

    District, permitted use, and whether an accessory dwelling unit is allowed at all.

  2. 02

    Dimensional review

    Lot size, setbacks, separation, height, coverage and parking against what is proposed.

  3. 03

    Services and constraints

    Utilities, septic or sewer, flood elevation, easements and association restrictions.

  4. 04

    Feasibility report

    A written answer: permitted as of right, permitted with a discretionary approval, or not permitted.

  5. 05

    Drawings

    Site plan and construction drawings prepared for submission, with engineering where required.

  6. 06

    Submission and corrections

    Filed by us, with correction responses handled through to permit issue.

Approvals

What review actually
looks at.

Zoning review comes first and asks whether the unit is allowed and whether it fits: use, lot size, setbacks, separation from the principal dwelling, height, lot coverage and parking.

Building review follows and asks whether what you have drawn complies: structure, egress, life safety, energy, and — in Miami-Dade and Broward, both inside the High-Velocity Hurricane Zone — product approval for windows, doors and roofing. Palm Beach County is not in the HVHZ and uses the statewide Florida Product Approval framework instead.

Utility and, where applicable, septic capacity run alongside on their own timetables.

INFILLED VEHICLE OPENINGBATHKITCHENLIVING / SLEEPINGENTRY

Simplified sketch, for explanation only. It is not a permit drawing and not a plan of either project shown on this page.

From first call to closeout

  • Zoning verification

    Whether the use is permitted at the address.

  • Dimensional compliance

    Setbacks, separation, height, coverage and parking.

  • Survey

    A current boundary survey, which most submissions require.

  • Site plan

    Showing compliance with each dimensional requirement.

  • Construction drawings

    For building review.

  • Engineering

    Where structure or new construction requires it.

  • Discretionary approval

    Variance or administrative adjustment where needed.

  • Building permit

    Submission and correction responses.

  • Utility applications

    Each provider on its own timetable.

  • Inspections

    Through construction to final.

Miami-Dade has a real ordinance; the state does not have a mandate

County Code section 33-22 is genuine and applies inside the Urban Development Boundary in specified districts. What does not exist is a statewide requirement obliging every municipality to allow accessory dwelling units — that legislation failed in 2026.

Nothing here is legal advice, and no approval outcome or review duration is promised. Requirements vary by municipality and by property.

Cost and schedule

What moves the number

Permitting cost is driven by how far your parcel sits from a straightforward as-of-right approval.

01

What moves the cost

  • As of right, or not

    A parcel that meets every requirement is the cheapest path. One needing a variance adds a discretionary process.

  • Whether a survey exists

    Most submissions require a current boundary survey, and many owners do not have one.

  • Conversion or new construction

    Converting existing space is a smaller documentation exercise than a new detached structure.

  • Engineering requirement

    New structures and structural alterations need engineered drawings.

  • Utility separation

    Whether separate meters or connections are required, which can be a significant line.

  • Correction cycles

    Complete first submissions cost less overall than cheap ones that attract corrections.

02

What moves the schedule

  • Feasibility

    Days rather than weeks, and worth doing before anything else.

  • Survey

    Scheduled with a surveyor; everything downstream waits on it.

  • Drawings

    Proportional to whether it is a conversion or new construction.

  • Zoning and building review

    Set by the authority having jurisdiction.

  • Discretionary approvals

    Variances run on published hearing calendars.

  • Utility applications

    Independent of the construction schedule.

Illustrative diagram · not a photograph of a project

AS FOUND · GARAGEopen vehicle opening · bare slab · no envelopeCONVERTED · HABITABLEinfill wall · windows · entry · egress · insulated envelope · treated slab010203040506

Six questions that
decide feasibility.

Before design, before budget, before anything. These six answers determine whether an accessory dwelling unit is possible at your address.

01

Is the use permitted?

Does the zoning district allow an accessory dwelling unit at all? This is the first question and sometimes the last.

02

Is the lot big enough?

Minimum lot size is common, and thresholds often differ between a conversion and a new detached unit.

03

Do the setbacks work?

Distance to boundaries, and required separation from the principal dwelling, constrain where a unit can physically sit.

04

Is there coverage left?

Lot coverage and floor-area limits may already be largely used by the existing house.

05

Where does parking go?

Many ordinances require parking for the unit, and it has to be shown on the site plan.

06

Can services reach it?

Water, sewer or septic capacity, and electrical service — sometimes requiring separate connections.

Open-plan studio ADU with the kitchen at one end, a grey sectional, bed and a doorway to the bathroom, under a vaulted ceiling
Elbaz Construction accessory dwelling unit, photographed on completion — the kind of unit these approvals lead to.

What to expect

Permitting is
mostly waiting.

The work is front-loaded and the waiting is unavoidable. What we control is that nothing waits for us.

  • Feasibility first

    You get a written answer before spending on design.

  • Survey early

    Most submissions need one, and it gates the site plan.

  • Complete submissions

    A thorough first submission attracts fewer corrections than a fast one.

  • Corrections are ours

    We answer plans examiners; you do not.

  • Discretionary hearings

    Where a variance is needed, expect a published calendar and a public process.

  • No promised outcomes

    We do not guarantee approval, and anyone who does is telling you something useful.

Questions

Ask the
awkward ones.

Six categories. Pick one and the answers change.

Not answered here?

(754) 236-0675

Sun-Fri 7am-7pm · Sat closed

No. Florida Statutes section 163.31771 permits local governments to allow accessory dwelling units; it does not compel them. Bills that would have created a statewide requirement did not pass — the House companion died in subcommittee on 13 March 2026. Whether you can build one depends entirely on your municipality and your parcel.

Miami-Dade County adopted an accessory dwelling unit ordinance in 2022, County Code section 33-22. It applies inside the Urban Development Boundary in specified zoning districts and sets minimum lot sizes, with a lower threshold for garage conversions than for new detached units. We verify the current requirements against your address rather than quoting a figure here.

Double-height ADU living room with a white entry door, skylight, wall-mounted television and a railed loft above
Project 02: living and sleeping sharing one volume.

Why Elbaz

What we will actually
put our name to

  • Licensed general contractor

    Licensed, bonded and insured · CBC1265280.

  • Feasibility before design

    A written answer on your parcel before you spend on drawings.

  • Regulatory claims checked

    We describe the law as it is — no statewide mandate, and a real Miami-Dade ordinance — rather than repeating what circulates online.

  • Corrections handled here

    Submission and correction responses are ours to make.

  • Design-build continuity

    The same contractor that permitted it can build it, so nothing is lost between the two.

  • Honest about variances

    We tell you when an approval is discretionary and outcome is not guaranteed.

Every claim in this column is something we can evidence. We have deliberately left out award badges, membership logos and project counts.

Reviews

I highly recommend them for home improvement. They renovated my master bathroom and a few upgrades for other guest bathrooms. They are very professional, courteous and transparent. They are great at communicating and finding ways to streamline the work. Sean has impeccable project management and customer relationship management skills. Very pleased with the work!

Omri B

Genuine Google reviews of Elbaz Construction, shown as written. None of these reviewers describes an ADU permitting engagement specifically, so none is presented as one.

Read them on Google

Redid my whole bathroom and kitchen. Great service - Great quality - very quick - very professional !! Highly recommended!

Adir Davidov

They are amazing! Very professional. Met my exact requests with so much patience and knowledge. They renovated my whole house and the whole process was such a breeze. I highly recommend them!

Lee Morali

We hired them to renovate our investment property and they provided exceptional quality service for an affordable price!

Shir Partush

Amazing experience with the entire company! They did a great job in my house for some work that needed to be completed, and I am extremely happy with the result. Super professional & great service. I highly recommend Elbaz Construction.

Mia Zafrani

After I've been Looking for a good company to renovate my house , I found those guys! These people are super professional super honest super Fast !! Don't hesitate to Rent their service! They are number one!!

carmit cohen

Start here

Tell us the address

What helps on the first call

The address or folio number, whether you have a survey, whether you are thinking conversion or new build, and whether an association is involved.

What happens next

We check zoning and the dimensional requirements against your parcel before anything is drawn.

What you will not get

A design produced before anyone has confirmed you are allowed to build it.

Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Find out whether
your parcel qualifies.

One feasibility check against your address, a written answer, and — if it is yes — drawings, submission and corrections handled through to permit.

Converted garage with grey stucco walls, a flat parapet roofline, a white-framed window and a panelled entry door with a glazed insert