What gets inspected at the factory?
Modular units are built under a state-approved plan and inspected by third-party agencies at the plant, so the structure, wiring, plumbing and mechanical work are checked before the modules ship. A local building inspector still reviews the foundation, set and site-side work, and signs off the certificate of occupancy.
How are modules shipped, and what holds up delivery?
Modules travel on trucks with escort rules, route limits, bridge and height restrictions, and permitted travel windows. Weather, an unready pad or a late crane can reschedule a day. We confirm the route and set day with the manufacturer and keep a backup date so the crane and crew are not paid to wait.
Which finishing jobs are still done on site?
Connections between modules, roof closure, exterior finishes at the seams, utility tie-ins, flooring or trim across joints, and paint touch-ups. Porches, garages and decks are usually site-built too. We list this site-side scope with the contract so each task has a trade and a place in the schedule.
Can a modular home sit on an elevated foundation in a flood zone?
Yes, as long as the foundation meets the flood-zone requirements and the engineer designs the connections for the loads. Elevated stem walls or piles lift the floor above base flood elevation, and the modules must be anchored. We design the foundation around the set, with the manufacturer's tolerances.
How are utilities connected after the set?
Plumbing, electrical and HVAC lines are stubbed out at the foundation and connected to the modules' shutoffs and panels. Sewer, water and power connections are inspected like a site-built home. Gas lines, meters and A/C condensers also need permits and testing. We coordinate each trade and the utility so the house can be energized.
What if a storm is forecast on set day?
We stop. Wind and lightning make crane work unsafe, and an open module is vulnerable to rain. The crane, trucks and crew get rescheduled together. Modules already set are weathered in as soon as possible with temporary covers and roof closure. We plan float into hurricane-season dates.
How do I choose a modular manufacturer?
Ask for state approval documentation, product approvals, wind-load ratings for your zone, sample plans and references for completed homes. Visit the plant if you can. Compare delivery terms, warranty coverage and who is responsible for transport damage. We review specifications with you and set up the site-side contract around them.
How much can I change after factory production starts?
Very little. Once modules are in production, layouts, window locations and structural details are locked, and changes can mean redrawing, re-inspection and delay. Finishes that are installed on site, such as paint colors, flooring or trim, can change later. We lock the design before the order is released and track options.