Project record
- Scope
- Whole-home renovation, occupied or vacated
- Typically includes
- Kitchen · bathrooms · flooring · electrical · plumbing · HVAC · interior doors and trim · paint · lighting
- Decided first
- Layout changes, structural openings, selections with long lead times
- Runs last
- Flooring, trim, paint and final fit-out, in that order
- Not included by default
- Roofing, windows, exterior envelope and site work — quoted separately when the house needs them
01
Survey and scope
Every room is measured and recorded, the electrical panel and service capacity are checked, and the existing plumbing and mechanical runs are traced. The scope is written down before anything is priced, because a whole-home number attached to a vague scope is not a number.
02
Design and selections
Layouts, elevations and a full selections schedule — tile, cabinetry, fixtures, hardware, paint — are settled before demolition. Long-lead items are identified and ordered early, because cabinetry and specialist tile are what most often hold a finished house hostage.
03
Rough-in while it is open
Electrical, plumbing, ductwork, waterproofing and any framing changes all happen in one window, then get inspected. This is the phase that justifies doing the whole house at once.
04
Finish, in order
Drywall, then tile, then cabinetry and counters, then flooring, then trim and paint, then fixtures and hardware. The order matters:
Does a renovation in a flood zone trigger extra code requirements?
If the home sits in a FEMA Special Flood Hazard Area, Florida’s substantial-improvement rule applies once a renovation or addition reaches 50% or more of the structure’s pre-improvement market value. Crossing that line means the entire structure, not just the new work, has to meet current flood-resistant construction standards under Florida Building Code, Residential Section R322. That is a structure-wide trigger, so it is worth checking against the appraised value early, before scope and budget are finalized.
Source: Florida Building Code, Residential Section R322 flood-resistant construction summary, Florida Division of Emergency Management.
reversing any two of those creates rework that nobody budgets for.