Sunrise · Broward County

One question decides where your application starts.

Sunrise publishes a routing test, and it is unusually clear: does the work change the outside of the building? Answer that correctly and the permit moves. Answer it wrongly and it sits in a queue that was never going to approve it.

The City's wording is precise. Permit applications for work that is new, or that enlarges, reduces or otherwise alters the exterior elevation of any building in Sunrise, must be presented to the City of Sunrise Community Development Department. A covered terrace, a pavilion, an addition, a changed opening - all of that is a change of elevation, whatever else it is.

The other route is just as explicit. Applications for work such as re-roofing, interior renovations, fencing, interior plumbing or electrical repairs and AC changeouts do not have to be evaluated by Planning & Development, and may be submitted directly to the Building Division. And before either of those, plans for demolition, additions, alterations or new construction must first be approved by Broward County.

The City also publishes the sensible escape hatch: if there is any question as to what type of work may be submitted directly, call the Building Division at (954) 572-2354 for a determination. That is the number to use rather than guessing, and it is the reason nothing on this page tells you which queue your particular project belongs in.

CBC1265280Florida certified building contractor. Licensed, bonded and insured.
Broward + 2All of broward, and miami-dade and palm beach.
4.8 / 343Average rating across Google reviews.
Two routesExterior elevation to Community Development; interior work direct to Building.

Does the work change the outside of the building? That decides everything.

What a Sunrise address changes

Six rules the City states in its own words.

City · county · state

01

The test is the exterior elevation

Work that is new, or that enlarges, reduces or otherwise alters the exterior elevation of any building, must be presented to Community Development. That is a question about the outside of the building, not about how big or expensive the job is.

02

Interior work has a direct route

Re-roofing, interior renovations, fencing, interior plumbing or electrical repairs and AC changeouts may be submitted straight to the Building Division, without going through Planning & Development at all.

03

Broward County can come before the City

Plans for demolition, additions, alterations or new construction must first be approved by the County. On those projects the City is not the first stop, and building the programme the other way round loses weeks.

04

The money moves at submittal

Permit and zoning fees, where zoning applies, are due and payable at the time of submittal rather than on issuance. That is a cash-flow fact worth knowing before the day you file.

05

A Control Number tracks the whole thing

The City issues one when it receives the application and plans, and it must be used to reference the permit throughout the approval process. Every later conversation starts with that number.

06

Every discipline has to clear it

A building permit is issued only after the application has been approved by all appropriate disciplines - structural, electrical, plumbing, mechanical and/or fire. The slowest reviewer sets the date, so the drawings are coordinated first.

City, county, state - we work out which of them your project meets.

Outside the building · 01

Work that changes what the house looks like

8 images · covered structures and terraces at several stages, on separate South Florida properties by Elbaz Construction · no municipality is documented, so none is claimed

Completed poolside cabana by Elbaz Construction, a dark steel frame with a timber slat soffit over a travertine deck, with a slatted privacy screen behind
The same cabana read from across the pool, its slat soffit and dark stone boundary wall seen end on, by Elbaz Construction
A garden pavilion part built: white columns standing on new footings under a timber-lined canopy, with a vertical slat screen closing one side
A long covered run newly framed over a poured slab at the rear of a single-storey house, the ground either side still raw, by Elbaz Construction
A finished covered terrace running the length of a house on dark posts with a white soffit and ceiling fans, on an Elbaz Construction project
A freestanding pavilion on a pale paved base set into artificial turf, with a slat screen to one side, built by Elbaz Construction
A covered travertine terrace on white posts beside sliding doors, with ceiling fans and the planting beyond, by Elbaz Construction
A dark-framed covered terrace over large-format stone paving with a pebble drainage margin being completed, on an Elbaz Construction project

A cabana finished. Every line of it changes the exterior of the property, which is what decides where the application goes first.

1 / 8

New covered structures alter an elevation. That sets the route.

What the photographs show

The first gallery changes an elevation. The second does not.

The structures above are covered terraces, cabanas and pavilions, photographed at stages from a poured slab and standing columns through to a finished slat soffit over travertine. Every one of them is the kind of work the City means by new work that alters the exterior elevation of a building, which is why it is the first gallery on a page about routing.

The kitchen below it is the other case. A hob, an extractor, a run of granite, a sink and its supply - substantial work, several disciplines, and none of it visible from the street. That is the sort of thing the City names as submittable directly to the Building Division.

The difference between the two galleries is not size or cost. It is whether the outside of the building changes.

Neither gallery tells you which queue your own project belongs in, and deliberately so. What they do show is the distinction the City draws, which is the one worth understanding before a drawing is finished.

A note on the photographs. They are our own projects, and the record is deliberately thin: no address, no client, no contract value, no dates. We do not claim any of them is in Sunrise. They are here because the first gallery is the kind of work that changes an exterior elevation and the second is the kind that does not, which is the distinction this whole page turns on.

Observed specification
StructuresFreestanding and attached canopies on steel or timber posts
SoffitsTimber slat and flat white, with recessed lighting and ceiling fans
DecksTravertine, large-format stone and pavers, with drainage margins
KitchenGrey shaker units, granite worktops, linear mosaic splashback
Kitchen servicesGas hob with island extractor, double range, undermount and apron-front sinks
Not documentedMunicipality, address, client, contract value, dates and area

Described only from what these photographs show, together with the general requirements that govern work of this kind in Broward County. The exterior frames are several separate properties and are not presented as one project. Nothing here is claimed to be in Sunrise.

Send us the scope and we will establish the route before we draw.

Detail

The routing test, applied

Photography: Elbaz Construction projects in South Florida

Completed poolside cabana by Elbaz Construction, a dark steel frame with a timber slat soffit over a travertine deck, with a slatted privacy screen behind

Community Development

Anything that changes the outside

New work, or work that enlarges, reduces or otherwise alters the exterior elevation of a building. A cabana, a canopy, an addition, a changed opening - all of it starts here in Sunrise.

Granite-topped island with a gas hob below a stainless island extractor, in a grey shaker kitchen by Elbaz Construction

Building Division

Straight through

Re-roofing, interior renovations, fencing, interior plumbing or electrical repairs, AC changeouts. The City names these as not needing Planning & Development at all.

A long covered run newly framed over a poured slab at the rear of a single-storey house, the ground either side still raw, by Elbaz Construction

Broward County

First, on the big ones

Demolition, additions, alterations and new construction are approved by the County before the City sees them. Programme it that way round.

A garden pavilion part built: white columns standing on new footings under a timber-lined canopy, with a vertical slat screen closing one side

The Control Number

Issued on receipt

Given when the City receives the application and plans, and used to reference the permit through the whole approval process.

The kitchen read down its length before styling, grey shaker units and a built-in oven tower over a large-format stone floor

All disciplines

Approved together

Structural, electrical, plumbing, mechanical and fire. The permit issues only once each of them has cleared it.

A finished covered terrace running the length of a house on dark posts with a white soffit and ceiling fans, on an Elbaz Construction project

Professional Day

Wednesday mornings

8:00 a.m. to noon, walk-in, no appointment. Plans examiners answer questions and review applications in person.

Community Development, Building Division, or the County first.

Finding the right queue

Sunrise: which department sees it first

Nearly every question we get asked here is really a routing question. The answers below are the City's own published rules, and where the City says to ring the Building Division for a determination, so do we.

It depends on one thing. The City states that applications for work that is new, or that enlarges, reduces or otherwise alters the exterior elevation of any building in Sunrise, must be presented to the Community Development Department. Work such as re-roofing, interior renovations, fencing, interior plumbing or electrical repairs and AC changeouts may go directly to the Building Division.

Then you ask rather than guess, and the City provides for exactly that: if there is any question as to what type of work may be submitted directly, call the Building Division at (954) 572-2354 for a determination. We make that call as a matter of course rather than filing on an assumption.

Yes, and often first. The City states that plans for work involving demolition, additions, alterations or new construction must first be approved by the County before the City process runs. On those projects the sequence is County, then City.

It is issued when the City receives the application and plans, and the City states it must be used to reference the permit throughout the approval process. In practice it is the single reference every later question hangs off.

At submittal. The City states that permit and zoning fees, where zoning applies, are due and payable at the time of submittal rather than at issuance. We do not publish any fee amount, because the City sets them and they change.

The Building Division designates each Wednesday between 8:00 a.m. and noon as Professional Day, when Building Plans Examiners are available to answer questions and review applications on a walk-in basis for construction and design professionals. No appointments are necessary, though they can be made for another time in the week.

The City states that plans may be checked out of the Building Division for correction, or corrected at the department during regular business hours. Either way the corrections come back into the same file against the same Control Number.

The City states that a building permit will be issued only after an application has been approved by all appropriate disciplines - structural, electrical, plumbing, mechanical and/or fire. That is why the drawings are coordinated across all of them before anything is filed.

Broward sits inside the High-Velocity Hurricane Zone, so glazing, doors and shutters need product approval accepted for HVHZ use. Replacing a window is also usually a change to the exterior elevation, which puts it on the Community Development route.

Yes, and it is the clearest example of the routing rule on this page: a new covered structure alters the exterior elevation, so the application is presented to Community Development, and if it counts as an addition the County sees it first.

We do not publish review durations or fee figures, because the authority sets both and they change. What we can control is that the application is complete, coordinated across every discipline and in the right queue on the first attempt.

Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Inside the building · 02

And work that the street never sees

6 images · one South Florida kitchen remodel · Elbaz Construction project photography · select to enlarge

Interior work the street never sees, and a different queue.

The sequence

Ten stages, and the routing decision comes before the drawings close

10 stages · County, City, department - in that order where it applies

01

The address and the permit record

What was approved, what was closed out and what was never either. It all exists before we do.

02

Measured survey

The building as it stands, inside and out, including every opening.

03

Establish the route

Does the work alter the exterior elevation, and does the County see it first? This is settled here, with a call to the Building Division where there is any doubt.

04

Design against the constraint

Scope tested against structure, setbacks and the envelope requirements that come with a Broward address.

05

Coordinate every discipline

Structural, electrical, plumbing, mechanical and fire resolved against each other, because the permit waits for the last of them.

06

County approval where it applies

Demolition, additions, alterations and new construction go to Broward County before the City.

07

File with the right department

Community Development or the Building Division, online through the City's portal or in person, with the fees payable at submittal.

08

Track it by Control Number

Issued on receipt and used for every conversation afterwards, with Professional Day available on Wednesday mornings for anything that needs a person.

09

Build - structure, envelope, services, finishes

Strip out and first fix, then the envelope with HVHZ-approved glazing and doors, then second fix and finishes.

10

Inspections and close-out

Booked with the Building Division, then close-out and the records handed over.

Which route a project takes and which approvals it needs are set by the property and the scope of work, and the determination is the City's. We confirm it before filing. We do not publish fees or review durations.

One licensed contractor from the survey to the final inspection.

Before the application goes in

Six things worth knowing while the drawings are still open

Owner’s guide · Sunrise

01

Does the work change the exterior elevation?

Anything new, enlarged, reduced or otherwise altered on the outside of the building goes to Community Development first. Settle this before the drawings are finished, not after they are filed.

02

Does the County need to see it first?

Demolition, additions, alterations and new construction go to Broward County ahead of the City. That ordering is the City's, and it shapes the programme.

03

Is every discipline actually resolved?

The permit issues only when structural, electrical, plumbing, mechanical and fire have each approved. One unresolved discipline holds all of them.

04

Is the fee budgeted for the day you file?

Permit and zoning fees are payable at submittal. It is a small thing that stops a filing on the day if nobody planned for it.

05

Have you used Professional Day?

Wednesdays, 8:00 a.m. to noon, plans examiners take questions and review applications on a walk-in basis, no appointment needed. An hour there is worth a fortnight of correspondence.

06

What does the permit record say about the house?

Earlier work that was never permitted or never closed out becomes your scope the moment you file. Establish it before design, not during demolition.

Which route a project takes is the City's determination, not ours. Where there is any question about what may be submitted directly, the City asks that the Building Division be called for a determination, and that is what we do. We do not publish fees or review durations.

Six things to settle while the drawings are still open.

Budget

What actually moves the number on a Sunrise job

Relative impact · not a quotation

01

Whether the exterior elevation changes

It decides the route, the drawings and often whether the County is involved at all. Two projects of the same value can sit in completely different processes because of it.

Highest impact
02

Structural work

New footings, posts and beams for a covered structure, or opening up a plan inside. It sets the drawing and the sequence.

High impact
03

How many disciplines are involved

The permit issues only when structural, electrical, plumbing, mechanical and fire have all cleared it, so each one added is another reviewer on the critical path.

High impact
04

Envelope work

HVHZ-approved glazing and doors, plus the making-good a non-standard opening always needs - and usually a change of elevation as well.

Moderate impact
05

What the permit record turns up

Earlier work never permitted or never closed out is resolved as its own scope.

Moderate impact
06

Specification of finishes

Real, but the most controllable line in the budget and the last one that should be used to rescue a number.

Lower impact

These weights describe what tends to move a number on work of this kind in Sunrise, in the order it tends to move it. Routing sits high on the list for a reason that has nothing to do with difficulty: an application in the wrong queue does not fail, it simply waits, and then starts again in the right one. None of these is a fee, a percentage or an estimate.

For a number specific to your house, we need to come and look at it.

Google reviews

What clients said on Google

4.8 Based on 343 Google reviews

★★★★★
Elbaz Construction provided excellent service and outstanding craftsmanship. The team was professional and attentive to our needs. We’re extremely satisfied with the results!
Damian Nunez · Google
★★★★★
We had a good time dealing with Asher and the crew, he went over and above all our expectations and made every effort to ensure that the end result was up to their high standards. Thank you !!
Emmett Giffin · Google
★★★★★
I give them a five star rating not only for their excellent roofing skills and timelines, but also for their competitive pricing and the honesty and professionalism of the team !! We are very pleased with the outcome
Zachary Gugliotta · Google
★★★★★
If you are planning to remodel your kitchen or bathroom or do any other construction project, call Sean from Elbaz Construction . He has a lot of experience and will recommend the best options/ suggestions to your project. He did high quality job !
Kameron Allison · Google
★★★★★
Asher has a lot of experience . We replaced our windows to energy efficient windows. He got down to business right away and did high quality work. His team is very professional! Thanks again
jessica berliner · Google
★★★★★
Asher was knowledgeable and gave us cool ideas that we didn't even know before. Nice beautiful color and design. We appreciate the price !
Sierra Bernabeo · Google

Review text is reproduced verbatim from the connected Google Business Profile, including its original spelling. Nothing is rewritten, shortened or combined, and no review schema is emitted on this page.

Join owners across Broward, Miami-Dade and Palm Beach.

Schedule a Consultation (754) 236-0675
Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Next step

Tell us what you want to build, and we will find out which queue it belongs in

Before a drawing is finished we establish whether the work alters the exterior elevation, whether the County sees it first, and which department the City wants it presented to - by asking them, not by assuming.