Every building department has a mental list of the reasons submittals come back. Very few write it down. Lake Worth Beach does: its plan review page names ten specific causes of delay, from an incomplete application and plans not stamped, signed or sealed as required by State Statute, through no up-to-date survey or site plan, improper setbacks and lot coverages, exceeding height requirements, inconsistencies between plans and product listings, accessibility not shown, and conflicts with the Land Development Regulations including use.

That is a gift, and it is worth treating as one. A list of failure modes published by the people who apply them is a better pre-submittal checklist than anything a contractor could write. It also contains one item that is easy to miss and expensive to miss: a lack of Certificate of Appropriateness application, if the property is located in a City historic district.

  • Ten named causes

    Published by the City on its own plan review page. Each one is something you can check before filing rather than discover after.

  • A historic district is a schedule item

    The City names a missing CoA application among its delay causes. Whether an address sits in a district is a City determination we check.

  • Either application is accepted

    The City states a permit application may be submitted with the Palm Beach County universal permit application, or a Lake Worth Beach one.

Talk through your property

Constraint and consequence

What the City warns about,
and what to do
with the warning.

None of the below is a statement about your address. It is what the City publishes about how reviews stall and what work is exempt, and what each item means for how a submittal should be built.

Grey stucco elevation of a converted garage with two white-framed windows above a lawn and concrete walkway
A completed Elbaz Construction elevation in South Florida. Setbacks, lot coverage and height are three of the ten delay causes this City publishes, and all three are decided by a drawing rather than by a material.

An out-of-date survey is a published delay

The City names "no up to date survey or site plan" among its causes. A current survey is a lead-time item, so it is commissioned at the start rather than chased at the end.

Signed and sealed, as the statute requires

Plans not stamped, signed or sealed as required by State Statute is another named cause. It is a workflow question for your design team, answerable in five minutes.

Accessibility has to be shown

The City names "access for handicapped not shown". Drawn, not assumed - it is about what appears on the sheet.

Product listings must agree with the plans

Inconsistencies between plans and product listings are named. Substituting a window late without updating the drawing creates exactly this.

The exemption list is measured

Not vague. Drywall repair under three 4-by-8 sheets; fence repair up to 16-foot sections, excluding pool barriers; soffit and fascia up to 25% of total; wood deck repair up to 100 square feet of previously permitted boards, no framing members.

Same-day inspection exists, for a fee

Next-day inspections are booked by 4:00 pm through the automated line. For a same-day inspection the City publishes a separate number and states that additional fees are assessed.

10

named causes of plan review delay the City publishes on its own page - which makes them ten things to check before filing

The same drawings, two submittals
ElementFiled on assumptionFiled against the list
The surveyThe one from the purchaseCurrent, and matching what is on site
SealingAssumed handledConfirmed against the statute before drawings are due
Setbacks and coverageChecked roughlyChecked against the Land Development Regulations
AccessibilityConsideredShown on the sheet
Historic districtAssumed not applicableConfirmed with the City, and a CoA filed if it is
What comes backComments, and a cycleA decision

The design is identical in both columns. What differs is whether ten published questions were answered before filing or after.

Stills from the two completed units on this page. They illustrate the stages; they are not photographs of the stage named beside them.

How we run it

Eight stages,
against a published list.

The sequence we follow on a Lake Worth Beach property. Several of the stages exist because the City named the failure they prevent.

  1. 01

    Address, record and district

    What the address is, what is already permitted on it, and whether the City treats it as being in a historic district. That last question is asked at the start in Lake Worth Beach, because the City lists a missing Certificate of Appropriateness among its own delay causes.

  2. 02

    Commission a current survey

    Named on the delay list, and a lead-time item. It is ordered in week one rather than assumed to exist.

  3. 03

    Test the scope against the exemptions

    The City publishes a measured exempt list. Some genuinely small work is exempt; most of what people assume is exempt is not. We check before promising anyone a permit-free job.

  4. 04

    Zoning envelope before layout

    Setbacks, lot coverage, building coverage and height are four of the ten named causes. They are checked against the Land Development Regulations before a layout is worth developing.

  5. 05

    Draw the things the list asks to see

    Accessibility shown rather than assumed, product listings consistent with the plans, disciplines complete, and everything stamped, signed and sealed as the statute requires.

  6. 06

    File digitally, on whichever form suits

    The City performs review digitally and accepts either its own application or the Palm Beach County universal permit application, with a master permit application used for all scopes of work and one copy of submittal documents.

  7. 07

    Build, with inspections booked to the clock

    Next-day inspections requested through the automated line by 4:00 pm. Where the programme genuinely needs it, the City publishes a same-day route with additional fees assessed.

  8. 08

    Closeout

    Through the inspections the scope requires, then the permit is closed out rather than left open against the property.

Approvals

What is exempt,
and what is not.

Lake Worth Beach is unusually precise about small work. Its published permit exceptions are written to a measurement rather than to a feeling: drywall interior wall repair of less than three 4-foot by 8-foot sheets; fence repair or replacement of a previously permitted fence up to 16-foot sections, excluding pool barriers; soffit and fascia repair and replacement up to 25% of the total; wood deck repair up to 100 square feet of previously permitted deck boards with no framing members; plumbing fixture replacement for a single family or R-3 occupancy in the same location, excluding bath tub and shower; and appliance replacement with cord and plug, excluding water heaters.

Everything outside those lines is a permit. The City states that building permits are required to construct, modify, repair, demolish or alter buildings, and that work without a permit may result in code compliance action. The precision cuts both ways - it tells you exactly what you may do, and exactly where that stops.

INFILLED VEHICLE OPENINGBATHKITCHENLIVING / SLEEPINGENTRY

Simplified sketch, for explanation only. It is not a permit drawing and not a plan of either project shown on this page.

From first call to closeout

  • Drywall

    Interior wall repair of less than three 4-foot by 8-foot sheets. Beyond that it is a permit.

  • Fences

    Repair or replacement of a previously permitted fence up to 16-foot sections - and the City explicitly excludes pool barriers from that exemption.

  • Soffit and fascia

    Repair and replace up to 25% of the total. A whole run is a different job.

  • Wood decks

    Repair up to 100 square feet of previously permitted deck boards, with no framing members. Structure is not covered.

  • Plumbing fixtures

    Replacement of common household fixtures for single family or R-3, in the same location - excluding bath tub and shower.

  • Electrical

    Replacement of lights, outlets and switches for single family or R-3 per the National Electrical Code edition the City cites.

  • Appliances and air conditioning

    Appliance replacement with cord and plug, excluding water heaters; and a window air conditioning unit in an existing opening with existing cord and plug.

  • Everything else

    A permit is required to construct, modify, repair, demolish or alter buildings, and the City states unauthorised work may result in code compliance action.

Precision is a favour

A city that says "up to 100 square feet, no framing members" has told you exactly where you stand. Vagueness is what makes people guess, and guessing is what produces unpermitted work that shows up at sale.

None of the above is a statement about your property. The City of Lake Worth Beach Building Division determines what any specific address and scope requires, including whether a property is in a City historic district, and requirements change. We confirm what your project actually needs before anything is filed, and we do not publish fees, review durations or any assurance of approval, because the City publishes none.

Cost and time

What moves the number,
and what moves the date.

No figures here. When a city publishes its own delay causes, the honest conversation about time is about which of them apply to you.

01

What moves the cost

  • Whether a Certificate of Appropriateness is in play

    In a City historic district it is a submittal in its own right, with its own considerations. Knowing early is the difference between a stage and a surprise.

  • How current the survey is

    Named on the delay list. A new survey costs what it costs; a stale one costs a review cycle.

  • The zoning envelope

    Setbacks, coverage and height decide what is worth drawing. Testing them first is cheaper than redrawing after.

  • Product selection and its paperwork

    Inconsistencies between plans and product listings are a named delay cause, so a late substitution has a documentation cost.

  • Structural alteration

    Openings, spans and load paths need engineering, and engineering needs to be in the drawing before it can be in the submittal.

  • What the survey and demolition find

    On an older Lake Worth Beach property, previous work - permitted or not - is discovered and has to be resolved rather than covered.

02

What moves the schedule

  • Getting a current survey

    A lead-time item, and one of the City’s own named causes of delay.

  • The Certificate of Appropriateness route

    Where it applies. It is a real stage and it belongs in the programme from the start.

  • Digital plan review

    The City performs review digitally, and once all appropriate departments have reviewed, the permit is sent by email or file transfer to the contractor of record.

  • Inspection booking

    Next-day requests by 4:00 pm through the automated line. Same-day is possible by calling for availability, with additional fees assessed.

  • Product lead times

    Ordering after approval is a date; ordering before it is a risk.

  • Closeout

    The inspections the scope requires, then the permit closed out rather than left open.

Owner’s guide

AS FOUND · GARAGEopen vehicle opening · bare slab · no envelopeCONVERTED · HABITABLEinfill wall · windows · entry · egress · insulated envelope · treated slab010203040506

Six things worth knowing
before you draw anything.

Not rules - the City writes those, and it determines them per address. These are the things that most often change how a Lake Worth Beach project is planned.

01

Read the delay list before the code

Ten named causes, published by the people who apply them. Working through them is the highest-value hour available before a submittal.

02

Ask about the historic district first

A missing Certificate of Appropriateness application is on the City’s own list. Whether your address is in a district is a City determination, and it is a two-minute question.

03

Get a current survey

Not the one from the closing file. "No up to date survey or site plan" is named as a delay cause, and it is entirely avoidable.

04

The exemptions are measured, so measure

Three sheets of drywall, 16-foot fence sections, 25% of soffit, 100 square feet of deck boards. If your job is bigger than the number, it is a permit.

05

Pool barriers are never the exempt fence

The City excludes them explicitly from the fence exemption. It is the single most safety-critical carve-out on the list.

06

Either application form is fine

The City accepts its own or the Palm Beach County universal permit application, and uses a master permit application for all scopes of work.

Bathroom with a dark shaker vanity and white stone top, black tapware, a sliding glass shower door on a black track and marble-effect porcelain wall tile
A completed Elbaz Construction bathroom in South Florida, photographed on completion. Not photographed in Lake Worth Beach.

What it is like

Living with a project
checked against a list.

The honest version of the experience, including the parts where we ask for things earlier than you might expect.

  • We ask about the district on day one

    Because the City put it on its delay list, and because the answer changes the programme rather than the finishes.

  • The survey gets ordered before the design

    It is named as a delay cause and it is a lead-time item. There is no good reason to leave it.

  • Decisions arrive in batches

    We will ask for product selections together, because inconsistencies between plans and product listings are one of the ten named causes.

  • One point of contact

    The same person from the first visit to the walkthrough. Design, permitting and construction sit in one company, so a reviewer’s comment does not wait on a hand-off between two firms.

  • The site itself is ordinary

    Protection, containment, deliveries, dust and noise are managed as on any job, and any association hours are respected without being asked.

  • Closeout is not optional

    Permits are closed out. An open permit stays with the property and reappears when it is sold, when it is someone else’s leverage.

Questions

Ask the
awkward ones.

Six categories. Pick one and the answers change.

Not answered here?

(754) 236-0675

Sun-Fri 7am-7pm · Sat closed

In the City’s own words: an incomplete permit application; plans not complete or missing required disciplines; plans not stamped, signed or sealed as required by State Statute; no up to date survey or site plan; improper setbacks, lot coverages and/or building lot coverages; exceeding height requirements; inconsistencies between plans and/or product listings; accessibility - access for handicapped not shown; lack of Certificate of Appropriateness application if located in a City historic district; and conflicts with the City’s Land Development Regulations, including use.

Because it converts a list of failure modes into a checklist. Every item is something you can verify before filing, and each one you verify is a review cycle you do not spend.

It is the approval that applies to work on property in a City historic district, and the City names a missing CoA application among its delay causes. Whether your address is in a district is for the City to say, and we check rather than assume.

We do not publish a number, because the City does not. It states that plan examiners make every effort to review plans as quickly as possible and then lists what delays them - which tells you where the leverage actually is.

White vanity with drawers and a lit mirror beside a framed glass shower screen over navy hexagonal tile
The entry of a completed Elbaz Construction conversion in South Florida. Not photographed in Lake Worth Beach. Access, thresholds and how someone gets through a building are among the things this City names on its delay list.

Why Elbaz

What we will actually
put our name to.

  • Licensed, bonded and insured

    Elbaz Construction is a licensed Florida general contractor, CBC1265280. Permits are pulled in the company’s name.

  • We work the City’s list before filing

    All ten of them, in writing, before a submittal goes anywhere. It is the cheapest quality control available on a project here.

  • We check the district rather than assume it

    A missing Certificate of Appropriateness is on the City’s own delay list. We get the answer from the City, not from a neighbour.

  • Design and construction in one contract

    The people who draw it are the people who build it, so a reviewer’s comment comes back to the team that can answer it.

  • We say what we do not know

    Whether an address is in a historic district, and what a specific scope needs, are the City’s to determine. Any contractor answering before checking is telling you something the City has not.

  • Permits closed out

    Every permit we pull is closed out at the end of the job rather than left open against the property.

No awards, no rankings and no numbers we cannot show you. Everything above is either public record or visible in the work on this page.

Reviews

I highly recommend them for home improvement. They renovated my master bathroom and a few upgrades for other guest bathrooms. They are very professional, courteous and transparent. They are great at communicating and finding ways to streamline the work. Sean has impeccable project management and customer relationship management skills. Very pleased with the work!

Omri B

Genuine Google reviews of Elbaz Construction, shown as written. None of these reviewers is identified as a Lake Worth Beach client and none is presented as one - they are shown because they are real, not because of where they are.

Read them on Google

Redid my whole bathroom and kitchen. Great service - Great quality - very quick - very professional !! Highly recommended!

Adir Davidov

They are amazing! Very professional. Met my exact requests with so much patience and knowledge. They renovated my whole house and the whole process was such a breeze. I highly recommend them!

Lee Morali

We hired them to renovate our investment property and they provided exceptional quality service for an affordable price!

Shir Partush

Amazing experience with the entire company! They did a great job in my house for some work that needed to be completed, and I am extremely happy with the result. Super professional & great service. I highly recommend Elbaz Construction.

Mia Zafrani

After I've been Looking for a good company to renovate my house , I found those guys! These people are super professional super honest super Fast !! Don't hesitate to Rent their service! They are number one!!

carmit cohen

Start here

Tell us about the property

What helps on the first call

The address, roughly when the house was built, what you want to change, and whether anything about the exterior is part of it. The address is what lets us check the historic district question rather than guess it.

What happens next

We check what is already permitted on the property, then survey it, and we work through the City’s own ten delay causes before anything is filed.

What you will not get from us

A promised review date, a fee quoted from a table, or an opinion about your historic district status. The City publishes none of those and neither will we.

Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Answer the ten questions
before the City asks them.

Lake Worth Beach has published exactly how a review goes wrong. Working through that list before filing is the cheapest thing anyone can do for a programme. Start with a survey and a conversation about which of the ten apply to you.

Shower detail with marble-effect porcelain walls, a recessed mosaic-lined niche and matte black rain head, handheld and valve