Miami Shores · Miami-Dade County

A Village that reviews the whole package at once.

Miami Shores publishes two rules about how it handles submissions that between them decide how long a straightforward job takes here. Neither is about design. Both are about completeness.

The first is at the front end: the Village states that all permit applications must include two copies of submittal documents, and that the permit fee is paid at submittal. A package that arrives short of either does not start moving.

The second is at the correction stage, and it is the one that catches people. The Village states that corrections will not be accepted if there are any disciplines pending review, and that partial corrections will not be accepted. So a set of comments has to be answered in full, and only once every discipline has reported. Sending back the structural fix while the plumbing reviewer is still working does not advance the file.

None of that is onerous, but it rewards a contractor who assembles the submission as one document rather than as a series of emails. The Village runs a Citizen Self-Service portal for submission, plan-review status by application number and inspection scheduling, and its counter is at 10050 NE 2nd Avenue.

CBC1265280Florida certified building contractor. Licensed, bonded and insured.
Miami-Dade + 2All of miami-dade, and broward and palm beach.
4.8 / 343Average rating across Google reviews.
One packageTwo copies at submittal, fee at submittal, corrections answered in full.

Filing in Miami Shores? The Village will not take a partial correction.

What a Miami Shores address changes

Six things that are true here and not everywhere.

Village · county · state

01

Corrections are answered in full or not at all

The Village states that partial corrections will not be accepted. Every comment in a cycle is closed out together, which means the response is assembled as one document rather than sent piecemeal as each consultant finishes.

02

And only once every discipline has reported

Corrections will not be accepted if there are any disciplines pending review. Waiting for the last reviewer before responding is not a delay - it is the process, and working against it simply loses a cycle.

03

Two copies, and the fee, at submittal

The Village states that all permit applications must include two copies of submittal documents and that the permit fee is paid at submittal. A package that arrives incomplete has not really arrived.

04

Status is tracked by application number

Plan-review status is available through the Village's Citizen Self-Service portal against the application number, so where a file actually sits is a matter of record rather than a phone call.

05

Miami-Dade sits inside the HVHZ

Glazing, doors, roofing and shutters need product approval accepted for high-velocity hurricane zone use. On the Village's older houses the openings are rarely a standard size, so survey precedes specification.

06

The setting is part of the brief

Generous setbacks and mature planting are the Village's character. What a room looks out onto is usually the strongest argument for where to open the plan up, and it costs nothing to design around.

Village, county, state - we work out which of them your project meets.

One open plan · 01

A kitchen opened towards the garden

8 images · one South Florida interior remodel by Elbaz Construction · the municipality is not documented, so none is claimed

Island with four upholstered stools facing a screened terrace and hedge, on an open-plan remodel by Elbaz Construction
Kitchen remodel by Elbaz Construction opening onto a screened terrace, with a stacked oven tower and concealed plinth lighting
Open-plan kitchen and living remodel by Elbaz Construction in South Florida, a veined porcelain island running out towards a seating area beyond
Handleless grey kitchen run with walnut wall units, twin ovens and an integrated induction hob, on an Elbaz Construction interior remodel
Handleless cabinetry, walnut wall units and a porcelain splashback carried up behind the hob, on an Elbaz Construction kitchen
Long view down a veined porcelain island to a tall walnut and white unit run, on an Elbaz Construction interior remodel in South Florida
Plinth-lit base units and a walnut tall run seen past the island edge, on an Elbaz Construction kitchen remodel
Portrait view of a veined porcelain island and stool run under a high ceiling, on an Elbaz Construction interior remodel

The garden side. In a Village of mature planting and generous setbacks, what the room looks out at is most of the reason to open it up.

1 / 8

This is what an open plan looks like once the coordination is done.

What the photographs show

The drawing that gets approved is the complete one

The remodel above is an open-plan kitchen and living room, photographed once the joinery, the porcelain and the lighting were in. It opens on the garden side, because in a house with this kind of outlook the view is the reason the plan gets opened at all.

Work like this touches several disciplines at once - structural, plumbing, electrical, sometimes mechanical - and in a jurisdiction that will not take a partial correction, that is precisely the case for drawing it fully before filing it. The coordination happens on paper or it happens in review cycles.

Where partial corrections are not accepted, coordination stops being a virtue and becomes the schedule.

A word on the photographs, since this page is about complete submissions. They are our own projects and the set is deliberately incomplete as a record: no address, no client, no value, no dates. We do not claim any of them is in Miami Shores, and we would not ask you to accept an evidence package this thin either.

Observed specification
RoomOpen-plan kitchen and living, single aspect onto a screened terrace
KitchenHandleless fronts with walnut wall and tall units
WorktopsVeined porcelain, mitred island edge, splashback in the same material
LightingRecessed downlights with concealed plinth lighting to base units
BathroomsWhite large-format tile, matt black brassware, lit recessed niches
Not documentedMunicipality, address, client, contract value, dates and area

Described only from what is visible in the photography, plus the general requirements that govern work of this kind in Miami-Dade County. The photography is shared with other municipality pages because it is one contractor's portfolio; no municipality is claimed for any frame.

Send us the address and we will tell you what the package needs.

Detail

A Village submission, component by component

Photography: Elbaz Construction projects in South Florida

Island with four upholstered stools facing a screened terrace and hedge, on an open-plan remodel by Elbaz Construction

The package

Complete, or not started

Two copies of submittal documents and the fee at submittal. The Village is explicit about it, and completeness is the one part of the timetable an owner genuinely controls.

White large-format tiled bath and shower with a sliding glass screen, matt black rail and a lit recessed niche, over a patterned blue and white floor

The correction cycle

All disciplines, all comments

No partial corrections, and none at all while a discipline is still pending. One consolidated response closes a cycle.

Handleless grey kitchen run with walnut wall units, twin ovens and an integrated induction hob, on an Elbaz Construction interior remodel

The envelope

Approved, then measured

HVHZ product approval narrows the choice; the opening decides what will actually fit. Surveying first avoids a permitted product that does not.

Long view down a veined porcelain island to a tall walnut and white unit run, on an Elbaz Construction interior remodel in South Florida

The structure

Drawn, not discovered

What is load-bearing is established before filing, because a structural change found later restarts more than the structural drawing.

Close detail of a lit recessed niche set into white large-format wall tile, on an Elbaz Construction bathroom

Waterproofing

Inspected, not assumed

Behind a niche, under a tray, up a wall - the part that decides whether the room is still sound in fifteen years.

Kitchen remodel by Elbaz Construction opening onto a screened terrace, with a stacked oven tower and concealed plinth lighting

The outlook

Worth designing around

Mature planting and generous setbacks are the Village's character. Where the plan opens should follow it.

Package, corrections, envelope, structure - in that order.

Assembling the package

Miami Shores: what the Village asks for

Most of what owners ask here turns out to be a question about the submittal rather than about the building work. Each answer below is what the Village itself publishes, with the parts that depend on your address left open.

With the Miami Shores Village Building Department, at 10050 NE 2nd Avenue. The Village states that all permit applications must include two copies of submittal documents and that the permit fee is paid at submittal. Submission, plan-review status by application number and inspection scheduling run through the Village's Citizen Self-Service portal.

Usually one of two published rules. The Village states that corrections will not be accepted if there are any disciplines pending review, and that partial corrections will not be accepted. So a response has to wait until every reviewer has reported, and then answer every comment together.

Not inherently - it makes an incomplete submission slower. A package assembled in full, and a correction answered in full, moves through the same number of cycles as anywhere else. Most of the lost time we see elsewhere comes from responding piecemeal, which simply does not work here.

Miami-Dade is inside the High-Velocity Hurricane Zone, so glazing, doors and shutters need product approval accepted for HVHZ use. On the Village's older houses the practical constraint is usually the opening size, so we survey before anything is specified.

Often, but it is a structural question first, and in a jurisdiction that reviews the whole package it is one to settle before filing rather than during review.

Yes. Permitting, structure, envelope and finishes sit under one licence, and assembling a complete package is part of the job rather than something you are sent away to arrange.

We do not publish review durations or fee figures, because both are set by the authority and change. What we can do is make sure the submission is complete, which is the part that actually moves the date here.

Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Wet rooms · 02

The rooms a family bathroom has to be twice

6 images · bathrooms from the same interior programme · Elbaz Construction project photography · select to enlarge

One family bathroom usually has to do two jobs.

How the work runs here

From the survey to the final inspection

10 stages · coordinated before filing, not during review

01

The address and the record

Permit history, what was approved and what was closed out. All of it exists before we do.

02

Measured survey

The house as it stands, including the openings, because the specification depends on them.

03

Scope against constraints

What you want, tested against the structure, the setbacks and the flood position.

04

Coordinate every discipline on paper

Structural, plumbing, electrical and mechanical resolved against each other before anything is filed - which is what a package review rewards.

05

Assemble the complete package

Two copies of submittal documents, the fee at submittal, and nothing left to follow on later.

06

File and track by application number

Submitted through the Village's Citizen Self-Service portal, with status followed against the application number.

07

Answer corrections in one response

Once every discipline has reported, all comments are closed out together.

08

Strip out and first fix

Demolition, then drainage, power and structural work, inspected as the code requires.

09

Envelope, second fix and finishes

HVHZ-approved glazing and doors, then joinery, stone and porcelain, brassware and lighting.

10

Inspection and close-out

Final inspections, close-out and the records handed over, so the next owner inherits paperwork rather than a mystery.

Which approvals a project needs depends on the property and the scope. We confirm the Village's current submission requirements for your address before filing. We do not publish review durations or fees.

One licensed contractor from the survey to the final inspection.

Before you submit

Six checks that decide whether a file keeps moving

Owner’s guide · Miami Shores

01

Is the package genuinely complete?

Two copies of submittal documents, and the fee, at submittal. Completeness is the single biggest lever you have over the calendar here, and it is entirely within your control.

02

Has every discipline reported before you respond?

Corrections are not accepted while any discipline is still pending. Check the status against the application number before assembling a response.

03

Does the response answer every comment?

Partial corrections are not accepted. One consolidated response, covering all disciplines, closes a cycle; a partial one does not open the next.

04

What does the record say about the house?

Earlier additions, enclosures and conversions carry whatever was approved at the time. Establish that before design, not during demolition.

05

Are the openings surveyed?

HVHZ product approval narrows the choice, and an older opening rarely matches a standard unit. Measure before specifying.

06

What is load-bearing?

Opening a compartmented plan is a structural question. The answer sets the layout and it belongs at the start of the drawing, not the end.

Which of these apply, and what each requires, is set by the property and the scope of work. We confirm the Village's current submission requirements for the specific address before filing, and we do not publish review durations or fees.

Six checks, and completeness is the one you fully control.

Budget

What moves a Miami Shores number

Relative impact · not a quotation

01

Structural change

Opening a compartmented plan means establishing and replacing what is holding the house up. It is the item that most changes a number on this stock.

Highest impact
02

Size and complexity of the scope

Area, number of wet rooms and how many services move. Complexity costs more per square foot than area does.

High impact
03

Coordination and drawing depth

A package review rewards drawings that are complete. That work is real, it is front-loaded, and it is cheaper than losing review cycles.

High impact
04

Envelope work

HVHZ-approved glazing and doors, plus the making-good that non-standard openings always need.

Moderate impact
05

What the record turns up

Earlier work that was never permitted or never closed out is resolved as its own scope.

Moderate impact
06

Specification of finishes

Real, but the most controllable line in the budget and the last one that should be used to fix a number.

Lower impact

These weights describe what tends to move a number here, in the order they tend to move it. Where the Village will not take a partial correction, the cost of getting the package wrong is a whole review cycle rather than a line item, which is why completeness sits so high. Nothing here is a fee, a percentage or a quotation.

For a number specific to your house, we need to look at it.

Google reviews

What clients said on Google

4.8 Based on 343 Google reviews

★★★★★
Elbaz Construction provided excellent service and outstanding craftsmanship. The team was professional and attentive to our needs. We’re extremely satisfied with the results!
Damian Nunez · Google
★★★★★
We had a good time dealing with Asher and the crew, he went over and above all our expectations and made every effort to ensure that the end result was up to their high standards. Thank you !!
Emmett Giffin · Google
★★★★★
I give them a five star rating not only for their excellent roofing skills and timelines, but also for their competitive pricing and the honesty and professionalism of the team !! We are very pleased with the outcome
Zachary Gugliotta · Google
★★★★★
If you are planning to remodel your kitchen or bathroom or do any other construction project, call Sean from Elbaz Construction . He has a lot of experience and will recommend the best options/ suggestions to your project. He did high quality job !
Kameron Allison · Google
★★★★★
Asher has a lot of experience . We replaced our windows to energy efficient windows. He got down to business right away and did high quality work. His team is very professional! Thanks again
jessica berliner · Google
★★★★★
Asher was knowledgeable and gave us cool ideas that we didn't even know before. Nice beautiful color and design. We appreciate the price !
Sierra Bernabeo · Google

Review text is reproduced verbatim from the connected Google Business Profile, including its original spelling. Nothing is rewritten, shortened or combined, and no review schema is emitted on this page.

Join owners across Miami-Dade, Broward and Palm Beach.

Schedule a Consultation (754) 236-0675
Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Next step

Bring us the address, and we will assemble the file

We will tell you what the Village needs in the package, coordinate the disciplines before anything is filed, and answer corrections in one response - which is what actually keeps a Miami Shores file moving.