A restaurant build-out is not a fit-out with a kitchen in it. Health, fire and building each review it separately, the equipment dictates the services, and the only date that matters is the one you can open on.
Miami-Dade · Broward & Palm Beach Counties
ScrollResidential work — shown for build quality
IMPORTANT: these are RESIDENTIAL Elbaz Construction projects — outdoor kitchens, bar counters and covered dining structures. They are shown for build quality and detailing only. None of them is a restaurant, a commercial build-out, or a food-service project. We do not publish photography of client commercial premises. Select any frame to open it full size.
The service, defined
A restaurant build-out converts a shell or an existing tenancy into an operating food-service space: kitchen and its ventilation, grease waste, gas, refrigeration, front of house, restrooms, accessibility, fire protection, and every inspection that stands between the finished room and a licence to serve.
It differs from other commercial fit-out in one structural way — three separate authorities review it. The building department reviews construction. The fire authority reviews suppression, egress and the hood. The health authority reviews finishes, hand-washing, refrigeration and food-contact surfaces. They do not coordinate with each other. Sequencing their requirements is most of the job.

Three local realities set the programme. Electrical service capacity in older strip and street-front tenancies is frequently below what a modern kitchen draws, and a service upgrade runs on the utility’s schedule rather than yours. Grease interceptor sizing and location are set by the local authority and are the commonest late surprise on a build-out. And where the tenancy has outdoor seating — which in this climate is most of them — you are into a separate set of requirements for cover, egress and, near the coast, wind design on any structure you put over it.
Scope index
Thirteen items across five phases. Items one to four happen before any construction and they are where opening dates are made or lost.

What the tenancy actually gives you: electrical service capacity, water and waste positions, gas availability, structure above for hanging a hood, ceiling height, and whether the roof can take rooftop equipment. This survey decides whether the space is viable at your budget.
What the landlord’s work letter covers, what is your responsibility, approval requirements, insurance, and — the item that costs most when missed — when your rent actually starts.
The kitchen equipment schedule drives the entire services design. Gas, power, water, waste and ventilation all follow from it, and the long-lead items on it set the programme.
Kitchen workflow, front-of-house capacity, restrooms, accessible routes and the back-of-house circulation that health review will look at closely.
Building, fire and health each reviewing separately, each with their own requirements and timelines. Running these in the right order is a discipline, not an accident.
Existing fit-out removed back to what is being reused, with landlord requirements on hours, access, protection and waste routes respected.
Electrical distribution, plumbing, gas, and mechanical — including make-up air, which people remember only after the hood is installed.
Interceptor sized, located and installed to the local authority’s requirements, with the drainage that serves it. Frequently the item that moves the completion date.
Exhaust hood, ductwork to discharge, make-up air, and fire suppression over the cooking line — reviewed and inspected by the fire authority.
Floors, walls and ceilings in finishes health review accepts, hand-washing stations, equipment set and connected, and refrigeration.
Bar, servery, seating, lighting, acoustics and the finishes that decide what the room feels like — the only part of this list your customers will ever see.
Accessible routes, restrooms and fixtures to the requirements applying to your occupancy, shown on the drawings and verified on site.
Building, fire and health inspections through to the approvals you need to open, then handover with the documentation your operating licences depend on.
RESIDENTIAL Elbaz projects — shown for build quality, not as restaurants
We have no published photography of a completed restaurant build-out, and we are not going to present someone else’s work or a generated image as ours. What follows is genuine Elbaz Construction work on residential projects — built-in outdoor kitchens, bar counters with seating, and covered dining structures. It is here so you can judge the standard of the joinery, the services concealment and the covered structures. Every frame is residential. None is a restaurant.
Every frame above is a RESIDENTIAL Elbaz Construction project in South Florida, shown for build quality. None is a restaurant, a commercial build-out or a food-service facility.
Specification
A checklist of the requirements a food-service build-out has to meet, not a record of a specific project. Actual requirements are set by your municipality, your fire authority, your county health department and your lease. Verify yours before committing to a space.

Design and material language
The choices that people make on price or on instinct early, and what each one costs in weeks later.


Shell against existing restaurant
Judged on Elbaz residential built-in kitchen and bar work. Taking over a tenancy that was already food-service can save you the grease interceptor, the hood, the gas service and the electrical capacity — which is months, not just money.
Other options. A raw shell gives you a free hand and makes you buy every piece of that infrastructure. Either can be right; signing the lease before finding out which one you have is never right.
Existing capacity or an upgrade
Judged on Elbaz residential built-in kitchen and bar work. Confirming the available service against your equipment schedule before signing. It is a survey and a calculation, and it takes days.
Other options. Discovering you need a service upgrade after signing puts your opening on the utility’s programme, which no contractor controls and no amount of money accelerates reliably.
Sized as a system
Judged on Elbaz residential built-in kitchen and bar work. Exhaust hood, duct route to discharge and make-up air designed together, with a structural route for the duct confirmed early.
Other options. Sizing the hood and forgetting the make-up air produces a kitchen that pulls air from the dining room, holds doors shut and never quite clears. Fixing it after ceilings close is expensive and disruptive.
Sized and located early
Judged on Elbaz residential built-in kitchen and bar work. Confirmed with the local authority during design, including where it goes and how it gets serviced.
Other options. This is the most common late surprise on a build-out. Discovering the required size will not fit where you assumed can mean excavation, a redesign of the drainage, or both — at the end of the programme.
Where the money shows
Judged on Elbaz residential built-in kitchen and bar work. Lighting, acoustics and surfaces, which is where the room’s character actually comes from — and acoustics is what customers feel and rarely name.
Other options. Spending the finish budget on decoration while under-specifying lighting and acoustics produces a room that photographs well and is unpleasant to sit in on a full night.
On what is shown. No image on this page is a restaurant, a commercial build-out, a food-service facility, or work by anyone other than Elbaz Construction. Every photograph is a RESIDENTIAL Elbaz project shown for build quality, and is captioned as such. The diagram below is an original illustrative drawing prepared for this page.
Process
The first two happen before you sign a lease, because that is the last point where the information is worth anything.
What the tenancy gives you — before signing, ideally.
Work letter scope, approvals and rent commencement.
The kitchen list that drives every service.
Kitchen workflow, front of house, restrooms and accessibility.
Building, fire and health, sequenced deliberately.
Strip out, then MEP, gas and grease waste.
Exhaust, duct, make-up air and suppression installed.
Health-compliant finishes, equipment set and connected.
Bar, seating, lighting, acoustics and finishes.
Building, fire and health through to approval to open.
Technical brief
Building, fire and health each review your restaurant separately, each with their own requirements. The sequence you run them in is the difference between opening on time and paying rent on an empty room.


How the space is classified drives egress, accessibility and construction requirements. A change of use from retail to food service triggers requirements the previous tenant never had to meet.
Accessible route, restrooms, counters and seating. It is a drawing-stage decision, and it is verified on site — a build-out that ignores it does not open.
Capacity, travel distance, door swings, hardware and emergency lighting, based on the occupant load you are designing for.
The exhaust hood over the cooking line and its fire suppression system are reviewed and inspected by the fire authority, separately from the building review.
Grease duct routing, clearances and discharge location are prescribed. Finding a compliant route through an existing building is a design problem to solve early.
Detection, alarm and portable extinguishing to the requirements for your occupancy and your fire authority.
Floors, walls and ceilings in food-preparation areas have to be smooth, cleanable and non-absorbent to the health authority’s standard. This is specified on the drawings, not chosen on site.
Hand-wash stations where required, plus the sink configuration for warewashing and food preparation your operation needs.
Cold storage capacity, dry storage separation and how waste is handled and stored.
Sizing and location to the local authority’s requirement, with access for servicing. Confirm this during design, not during construction.
Work letter scope, drawing approval, insurance, hours, access, and rent commencement — which frequently starts before you can open.
An electrical service upgrade or a new gas service runs on the utility’s schedule. Identify the need in week one or it becomes the last item on your programme.
Disclaimer. Requirements are set by your municipality, your fire authority, your county health department and your lease. Nothing here is a legal opinion or a substitute for confirming your own requirements. Licensing to operate a food-service establishment is separate from construction permitting and is obtained by the operator.
Assembly
An original illustrative diagram prepared for this page. It shows the relationship between the cooking line, the exhaust hood, the duct to discharge and the make-up air that replaces what is extracted. It is not a design drawing and not from any project.
A hood extracting a large volume creates negative pressure unless make-up air replaces it. The symptoms are doors that will not open, a kitchen that never clears and conditioned air pulled straight out of the dining room.
Grease duct has prescribed clearances and a required discharge location. In an existing building, finding a compliant route through structure is a design task that belongs at the start.
The fire authority reviews and inspects the suppression system over the cooking line on its own schedule, independent of the building inspection.
In this climate, replacement air is a real cooling load. Under-sizing the system to save capital cost shows up in every energy bill and in a dining room that never holds temperature on a full night.
Performance and quality
No opening date, programme length, cost or capacity is claimed on this page, and no restaurant project is presented as ours. Those come from your space, your equipment schedule and your jurisdiction.


Cost and timeline
We do not publish prices for build-outs. The range between a former restaurant with working infrastructure and a raw shell is enormous, and that difference is settled before construction starts. We price after the space is surveyed and the equipment schedule exists.


| # | Variable | Why it moves the number |
|---|---|---|
| 01 | Shell or former restaurant | The single largest variable. Existing infrastructure can remove months and a large share of the cost. |
| 02 | Electrical service | Whether the existing capacity serves your equipment, or a utility upgrade is required. |
| 03 | Gas service | Availability, pressure and whether a new service or upgrade is needed. |
| 04 | Grease interceptor | Sizing, location, excavation and drainage modification. |
| 05 | Hood and make-up air | Hood, duct route, discharge, make-up air unit and suppression. |
| 06 | Kitchen equipment | Owner-supplied or contractor-supplied, and how long the long-lead items take. |
| 07 | Refrigeration | Walk-in cold storage, reach-ins and the services they need. |
| 08 | Health-compliant finishes | Floors, walls and ceilings meeting the health authority’s standard in preparation areas. |
| 09 | Front-of-house specification | Bar, seating, lighting, acoustics and finishes — a wide range at identical area. |
| 10 | Accessibility works | Restrooms, routes and fixtures where the existing space does not comply. |
| 11 | Permits and reviews | Building, fire and health fees, reviews and inspections. |
| 12 | Landlord requirements | Insurance, hours, access, protection and any work the lease puts on you. |
| 13 | Programme length | Every week of construction is a week of rent before revenue, which belongs in the cost of the decision. |
Question index
Fifteen questions on space selection, reviews, kitchen infrastructure, programme and cost. Requirements are set by your municipality, fire authority, health department and lease — verify yours.
A former restaurant with working grease interceptor, hood, gas service and adequate electrical capacity can save you months and a large share of the budget. A shell gives you a free hand and makes you buy all of it. The mistake is signing either before someone has surveyed what is actually there.
Electrical service capacity against your equipment schedule, gas availability, water and waste positions, whether a grease interceptor exists and is adequately sized, structure above for a duct route, ceiling height, and exactly when rent starts. That survey is inexpensive and it is the highest-value week of the project.
Usually well before you can open, and it is negotiable. It is a lease term, not a construction term, and it is worth negotiating with a realistic construction programme in hand rather than an optimistic one.
Because they regulate different things. Building reviews construction, structure, egress and accessibility. Fire reviews the hood, suppression and egress systems. Health reviews finishes, hand-washing, refrigeration and food handling. They do not coordinate with each other and they do not share a timeline.
It varies by jurisdiction, but the pattern is consistent: delay comes from an item discovered late rather than from any one authority being slow. Grease interceptor sizing and electrical service capacity are the two that most often arrive late and move the date.
Construction permitting and operating licensure are separate. The build-out has to be approved by health as constructed, and the licence to operate a food-service establishment is obtained by the operator. Both matter to your opening date.
It is replacement air introduced to balance what the hood extracts. Without it the kitchen runs at negative pressure — doors are hard to open, the kitchen never clears, and you are paying to condition air that goes straight up the duct. It is designed with the hood, not after it.
Your local authority sets the requirement, and it is confirmed during design alongside where the unit goes and how it will be serviced. Leaving it to construction is how projects end up excavating at the end of the programme.
Either works. What matters is that the equipment schedule is fixed early, because every service in the kitchen is designed from it, and that someone is tracking the lead times against the construction programme.
Then you need a utility upgrade, and that runs on the utility’s schedule. This is why it is checked before signing — it is one of the few items on a build-out that no contractor can accelerate.
Acoustics. A hard-surfaced room full of people is unpleasant at capacity and customers rarely name the reason — they just do not stay. Treating it during construction is straightforward; retrofitting it is not.
Frequently, and it is worth planning from the start. Cover, egress, accessibility and — near the coast — wind design on any structure you build over it all apply, and some are licensing questions as well as construction ones.
It depends on the space and the jurisdiction, and we will not quote weeks on a page. What we will do is give you a programme after the survey, with the long-lead items and the review sequence shown, so you can plan hiring and opening against something real.
Because two identical-looking tenancies can differ by an entire kitchen infrastructure. Service capacity, grease waste, hood and gas are the expensive items, and they are invisible when you walk the space.
We do not publish photography of client commercial premises, and we will not show you someone else’s project or a generated image as ours. The work shown on this page is residential and is labelled as such. If you want commercial references, ask us directly and we will discuss what we can share with the client’s consent.

Every frame referenced here is a RESIDENTIAL Elbaz Construction project, shown for build quality only. None is a restaurant or a commercial build-out.
Credentials and delivery
Nothing here is an award or a membership we cannot substantiate, and nothing here claims restaurant projects we cannot show you. The licence number is public and checkable.

CBC1265280 — certified building contractor, bonded and insured, holding the permit rather than brokering the job.
We look at a tenancy before you sign it, because that is when the information is still worth something.
The schedule is driven by long-lead items and the review sequence, because rent runs whether you are open or not.
Genuine Elbaz work building cooking lines, bar counters and covered dining structures — shown on this page as residential projects, because that is what they are.
We do not have published restaurant photography and we will not present anyone else’s work or a generated image as ours.
Building, fire and health coordinated by one party, so nothing falls between them.
Google reviews
Reviews are quoted verbatim from the Elbaz Construction Google Business Profile. They describe residential work and the company as a whole — none refers to a commercial or restaurant project.
★★★★★
“They are great at communicating and finding ways to streamline the work.”
Omri B · Google review
★★★★★
After I've been Looking for a good company to renovate my house, I found those guys! These people are super professional super honest super Fast !! Don't hesitate to Rent their service! They are number one!!
carmit cohen
★★★★★
Redid my whole bathroom and kitchen. Great service - Great quality - very quick - very professional !!
Adir Davidov
★★★★★
They renovated my whole house and the whole process was such a breeze. I highly recommend them!
Lee Morali
★★★★★
Amazing job Did a total renovation of my house with them
Elie Elancry
Proudly serving homeowners across Miami-Dade, Broward and Palm Beach
104 municipalities across three counties — and we hold the licence to build in all of them. Not sure about your address? Ask us.
Knowledge library
Adjacent work Elbaz delivers under the same licence.
Start here
Send us the address and your equipment list — or just the address. We will tell you what the tenancy actually gives you before you sign anything.