White rendered two-storey elevation with large window openings glazed, standing on a prepared site
A completed Elbaz Construction elevation in South Florida, glazing installed. What a design review looks at is exactly this: proportion, opening sizes, materials and how they meet.

Building here

Two approvals,
then a permit.

Coral Gables was drawn before it was built, and the City still runs that way. Its Board of Architects exists, in the City’s own words, "to ensure that the city’s architecture is consistent with the city’s regulations and to preserve the community’s traditional aesthetics", and it is made up of at least seven local architects appointed by the City Manager and approved by the City Commission.

The consequence for a project is a sequence, not a hurdle. The City states that for a typical building permit its review "would involve a preliminary and final board approval prior to permit issuance". Two decision points sit ahead of the permit, and the design has to be mature enough to survive both. That is a planning fact long before it is an aesthetic one.

  • The Board sits weekly

    It convenes every Thursday. A design that is ready in time is measured against a calendar that does not move for anyone.

  • Preliminary, then final

    The City describes a typical permit as needing both. Work that arrives half-resolved gets two conversations instead of one.

  • Standards are written down

    Section 5-100 of the Zoning Code sets the design review standards, and an appeal of the Board’s decision goes to the City Commission under Section 14-208.

Talk through your property

Constraint and consequence

What the City looks at,
and what it changes
about your programme.

The City publishes an itemised list of what each kind of work needs, and every entry on it is qualified "where applicable". None of the below is automatic. All of it is worth knowing before a schedule is committed.

Cooking wall with a stainless range, wall-mounted hood and marble splashback between tall cabinetry
A completed Elbaz Construction kitchen in South Florida. Interior work has its own permit category in Coral Gables — the City lists BATHROOM/KITCHEN/FLOORING/CEILINGS among the scopes with their own approvals.

Design review comes first

Where Board review applies, it sits ahead of the permit rather than beside it. Build it into preconstruction as a dated milestone, not as an administrative step that happens in parallel with ordering.

Colour is specified, not chosen later

The City requires applications to include "the Manufacturer’s Reference Code (e.g. Benjamin Moore, Sherwin Williams, etc.), Color Description and Color Number", and publishes pre-approved palettes from both. Colour becomes a submittal item.

Samples may be asked for

Elevations in colour may be required, a paint colour sample may be required, and "For Larger Projects, an Actual Sample Application on the Building may be required". Procurement should follow the approved selection, not anticipate it.

Appearance drives the category

Pavement is listed as "DRIVEWAYS/PAVERS/TILING/WALKWAYS — NEW OR CHANGE OF MATERIAL OR SHAPE". Changing what a surface is made of, or the shape it takes, is what puts it in the category — not simply that work is happening.

A design change can go back

The City states that if ironwork or railings permitted under a master permit "have changed in Design, the City Architect/Board of Architects will require another BOA Review for Approval", applied for under a permit revision. Mid-build redesign has a route, and the route costs time.

Photographs in colour, and only in colour

Submittals ask for colour photographs in PDF showing existing conditions of all scope items — the City writes "NO black & white photos Allowed". A small rule, and a fair signal of how the submittal is read.

7+

architects on the Board, appointed by the City Manager and approved by the City Commission, sitting every Thursday

The same project, planned two ways
ElementA city without design reviewCoral Gables
What is fixed firstStructure, then finishes as the job goesAppearance and materials, before the permit issues
ColourSelected during constructionSubmitted by manufacturer code, description and number
Roof and pavementA specification decisionNamed among what the Board considers, and keyed to material and shape
A change of mind mid-buildA variation to the contractMay require another review under a permit revision
Approvals before the permitOne review cyclePreliminary and final, for a typical permit
What the owner supplies earlyA budget and a briefA resolved design — which is what makes the budget real

Both routes are ordinary. The difference is where the decisions sit, and how much of the design has to be settled before anything is ordered.

Stills from the two completed units on this page. They illustrate the stages; they are not photographs of the stage named beside them.

How we run it

Eight stages,
design first.

The sequence we actually follow on a Coral Gables property. It is arranged around the City’s order of business rather than around ours.

  1. 01

    Property check

    What the address is, what is already permitted on it, and whether anything about it changes the route — designation, frontage, existing open permits. This is a records exercise and it happens before design opinions are formed.

  2. 02

    Survey and brief

    What you want, what the building will allow and what the site can take. On an existing house this is also where we find what a previous owner did without a permit, which is a live issue on any older Coral Gables property.

  3. 03

    Design to a reviewable standard

    Drawings developed to the point where a reviewer can actually judge them: elevations, materials, openings and the relationship between them. Section 5-100 sets the standards this is measured against.

  4. 04

    Selections, with their codes

    Colour by manufacturer reference, description and number. Roof tile, pavement material and shape, ironwork profile. These are submittal content in this city, so they are settled here rather than on site.

  5. 05

    Design review, where it applies

    The application goes in and, where Board review applies, through preliminary and final approval. We do not promise a date, because the City publishes none — what we do is make sure nothing in the submittal is the reason it takes two rounds.

  6. 06

    Permit and sub-permits

    Building Division review follows, with sub-permits applied for under the master permit once it issues. Documentation is resolved before mobilisation rather than chased during it.

  7. 07

    Construction

    Built to the approved design. If something genuinely has to change, we tell you what the change costs in review as well as in money — a design change to permitted ironwork, for instance, has its own route back through the City Architect or Board.

  8. 08

    Inspections and closeout

    Through the inspections the scope requires — the City’s own list includes a final historical inspection where applicable, final zoning, final public works and final building — and then the permit is closed out rather than left open.

Approvals

What the City asks for,
scope by scope.

Coral Gables publishes a permit requirements document that reads as a matrix: for each kind of work it lists the required approvals, the required inspections and, on a master permit, the sub-permits that follow once it issues. Every one of those columns is headed "where applicable" — the City’s own qualifier, and the reason this page will not tell you what your address needs.

What the list makes obvious is how much of it is about appearance. Roofs, pavement, fences, exterior walls, awnings, railings and ironwork, doors, skylights, windows and storefronts, landscaping, and exterior painting all have their own entries. So does the interior: bathrooms, kitchens, flooring and ceilings are a category of their own.

INFILLED VEHICLE OPENINGBATHKITCHENLIVING / SLEEPINGENTRY

Simplified sketch, for explanation only. It is not a permit drawing and not a plan of either project shown on this page.

From first call to closeout

  • Roofs, new or re-roof

    Roof tiles are named among what the Board considers. Roofing also carries the Miami-Dade High-Velocity Hurricane Zone application forms, an owner’s notification for roofing considerations and a hurricane mitigation affidavit.

  • Exterior painting

    Listed for both commercial and residential exteriors, with residential shown specifically as a paint colour review. Applications carry the manufacturer’s reference code, colour description and colour number.

  • Driveways, pavers, tiling and walkways

    The City’s own heading is "new or change of material or shape" — which is the test, and it is about what the surface becomes rather than about the fact of working on it.

  • Doors, skylights, windows and storefronts

    Their own category, and in Miami-Dade County the products themselves carry approval documentation that has to match what is physically installed.

  • Railings, guardrails and ironwork

    Permitted under the master permit — and if the design later changes, the City states that the City Architect or Board will require another review, applied for as a permit revision.

  • Bathrooms, kitchens, flooring and ceilings

    Interior work is not outside the system. It has its own entry, its own approvals where applicable and its own inspections.

  • Landscaping and trees

    A tree protection plan is called for, referencing the City’s own Commission resolution, and the City states plainly that a survey cannot serve as one.

  • Demolition, partial or total

    Removing exterior features, landscaping or accessory structures without replacement construction is its own category, which is worth knowing before anything is taken down to "see what is there".

The submittal is the schedule

Almost every delay we have seen in a design-review city is a submittal that arrived before the design was resolved. Two rounds of review is not a slower city — it is usually an earlier drawing.

None of the above is a statement about your property. The City of Coral Gables Development Services Department determines what any specific address and scope requires, its published requirements are qualified "where applicable" throughout, and requirements change. We confirm what your project actually needs before anything is filed, and we do not publish fees, review durations or any assurance of approval, because the City publishes none.

Cost and time

What moves the number,
and what moves the date.

No figures here. In a city where the design is reviewed before the building is, the same square footage can carry very different amounts of drawing, selection and coordination — and that is where the difference lives.

01

What moves the cost

  • Design resolution

    A design taken to a reviewable standard costs more in drawing and less in everything downstream. It is the single best-value line in the budget here.

  • Material and finish selection

    Roof tile, pavement, ironwork, glazing and colour are specification decisions with submittal consequences, so they are made deliberately rather than late.

  • Structural alteration

    Openings, spans and load paths need engineering, and engineering needs to be in the drawing before it can be in the submittal.

  • The condition of what is there

    On an existing house, what a previous owner did — permitted or not — is found during survey and demolition and has to be resolved rather than covered.

  • Scope that touches the exterior

    Anything visible has more people looking at it. That is not a penalty; it is the reason the city looks the way it does.

  • Scope added after submittal

    The most reliable way to turn one review cycle into three.

02

What moves the schedule

  • Getting the design ready

    The longest genuinely controllable part, and the one an owner most affects by making decisions when they are asked for.

  • Design review, where it applies

    The City describes a preliminary and a final approval for a typical permit and publishes no duration. We plan around the sequence, not around a promise.

  • Building Division review

    Follows design approval, with comments answered by revising and resubmitting through the City’s portal.

  • Product and material lead times

    Approved selections can have long lead times. Ordering before approval is a risk; ordering after approval is a date.

  • A mid-build change of mind

    May carry a permit revision and, for some scopes, another review. Worth pricing in time as well as money.

  • Inspections

    Sequenced through construction, with the closeout inspections the scope requires at the end.

Owner’s guide

AS FOUND · GARAGEopen vehicle opening · bare slab · no envelopeCONVERTED · HABITABLEinfill wall · windows · entry · egress · insulated envelope · treated slab010203040506

Six things worth knowing
before you draw anything.

Not rules — the City writes those, and it qualifies them. These are the things that most often change how a Coral Gables project is planned.

01

Decide the look before you price the job

In a city that reviews design ahead of permit, a budget built on an unresolved design is a guess. The order that works is: resolve, submit, price, build.

02

Colour is a document

Manufacturer reference code, colour description, colour number — and the City publishes pre-approved palettes from Benjamin Moore and Sherwin Williams on its own Board of Architects page. Start there and the conversation is shorter.

03

"Where applicable" is doing real work

The City’s requirements matrix qualifies almost every line. Two neighbouring properties can genuinely need different things, which is why nobody should tell you what yours needs without checking it.

04

Material and shape are the trigger for surfaces

For driveways, pavers, tiling and walkways the City’s heading is new or change of material or shape. Like-for-like and a redesign are different questions.

05

Changing your mind has a route

It is not forbidden — it is procedural. A design change to permitted ironwork goes back through the City Architect or Board under a permit revision. Knowing that in advance is what makes it a decision rather than a shock.

06

The Mediterranean bonus is not for your house

The City’s Med Bonus, under Section 5-200, grants additional floor area ratio and storeys — to multi-family and mixed-use buildings that meet a set number of requirements. It is a genuine incentive and it is not a single-family programme.

Completed structural shell of a two-storey waterfront house with glazing installed, on a prepared and levelled lot
A completed Elbaz Construction structural shell in South Florida, glazing installed. Photographed during construction, not in Coral Gables.

What it is like

Living with a project
that is being looked at.

The honest version of the experience, including the parts that are slower here than they would be somewhere without a design review.

  • The front of the job is quiet

    More of the work happens in drawings and selections than owners expect, and less on site early. That is the trade this city makes.

  • Decisions arrive in batches

    We will ask for colour, tile, pavement and ironwork together rather than one at a time, because they go into the same submittal.

  • You will hear "where applicable" from us too

    Because that is what the City writes. We tell you what we are confident about and what we are going to confirm, and we keep the two apart.

  • One point of contact

    The same person from the first visit to the walkthrough. Design, permitting and construction sit in one company, so a reviewer’s comment does not wait on a hand-off between two firms.

  • The site itself is ordinary

    Protection, containment, deliveries, dust and noise are managed as on any job. Neighbours and any association hours are respected without being asked.

  • Closeout is not optional

    Permits are closed out. An open permit stays with the property and reappears when it is sold, when it is someone else’s leverage.

Questions

Ask the
awkward ones.

Six categories. Pick one and the answers change.

Not answered here?

(754) 236-0675

Sun-Fri 7am-7pm · Sat closed

The City does not say that, and neither will we. It says the Board considers "a wide variety of building and development applications such as new residences, new commercial structures, pools, pavement, signs, roof tiles, all building expansions, etc.", and its permit requirements are qualified "where applicable" throughout. What your specific property and scope require is determined by the Development Services Department, and we confirm it before anything is filed.

In the City’s words it "was created to ensure that the city’s architecture is consistent with the city’s regulations and to preserve the community’s traditional aesthetics". It consists of at least seven local architects appointed by the City Manager and approved by the City Commission, and it convenes every Thursday.

The City states that for a typical building permit its review "would involve a preliminary and final board approval prior to permit issuance" — so two decision points sit ahead of the permit. In planning terms it means the design needs to be resolved earlier here than it would in a city with a single review.

Section 5-100 of the Coral Gables Zoning Code sets the design review standards. An appeal of the Board’s decision goes to the City Commission, under Section 14-208.

We do not publish a number, because the City does not. What we can tell you is which parts of your project are likely to attract review and what we do to keep it to one round — which is almost always a matter of how resolved the submittal is.

Barrel tile roof with a mortared ridge and two vent stacks against a clear sky
A barrel tile roof on a completed South Florida project. Roof tiles are named by the City among the things its Board of Architects considers.

Why Elbaz

What we will actually
put our name to.

  • Licensed, bonded and insured

    Elbaz Construction is a licensed Florida general contractor, CBC1265280. Permits are pulled in the company’s name.

  • Design and construction in one contract

    The people who draw it are the people who build it, so a reviewer’s comment comes back to the team that can answer it rather than crossing a company boundary.

  • We check the address before we form a view

    What is already permitted, what the scope will touch and what the City’s requirements say for it — confirmed, not assumed from a neighbour’s project.

  • We quote the design we submitted

    The selections in the submittal are the selections in the price. Colour, tile, pavement and ironwork are decided once.

  • We say what we do not know

    The City qualifies its own requirements "where applicable". Any contractor telling you exactly what your Coral Gables project will need before checking it is telling you something the City has not.

  • Permits closed out

    Every permit we pull is closed out at the end of the job rather than left open against the property.

No awards, no rankings and no numbers we cannot show you. Everything above is either public record or visible in the work on this page.

Reviews

I highly recommend them for home improvement. They renovated my master bathroom and a few upgrades for other guest bathrooms. They are very professional, courteous and transparent. They are great at communicating and finding ways to streamline the work. Sean has impeccable project management and customer relationship management skills. Very pleased with the work!

Omri B

Genuine Google reviews of Elbaz Construction, shown as written. None of these reviewers is identified as a Coral Gables client and none is presented as one — they are shown because they are real, not because of where they are.

Read them on Google

Redid my whole bathroom and kitchen. Great service - Great quality - very quick - very professional !! Highly recommended!

Adir Davidov

They are amazing! Very professional. Met my exact requests with so much patience and knowledge. They renovated my whole house and the whole process was such a breeze. I highly recommend them!

Lee Morali

We hired them to renovate our investment property and they provided exceptional quality service for an affordable price!

Shir Partush

Amazing experience with the entire company! They did a great job in my house for some work that needed to be completed, and I am extremely happy with the result. Super professional & great service. I highly recommend Elbaz Construction.

Mia Zafrani

After I've been Looking for a good company to renovate my house , I found those guys! These people are super professional super honest super Fast !! Don't hesitate to Rent their service! They are number one!!

carmit cohen

Start here

Tell us about the property

What helps on the first call

The address, roughly when the house was built, what you want to change, and whether anything about the exterior is part of it. The address is what lets us check the route rather than guess it.

What happens next

We check what is already permitted on the property, then survey it. What we price is what a survey found and what the City’s requirements say for the scope — not what a postcode implies.

What you will not get from us

A promised review date, a fee quoted from a table, or an assurance that anything will be approved. The City publishes none of those and neither will we.

Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Resolve the design,
then price the build.

In Coral Gables that order is not a preference — it is how the City works. Start with a survey and a conversation about what your project will actually be looked at for.

Open-plan kitchen with a large marble-topped island, dining table alongside and clear sightlines through to the living area