Does Elbaz Construction handle permits?

Yes. Elbaz Construction is a licensed Florida general contractor (CBC1265280) and pulls permits in its own name for the work it builds across Miami-Dade, Broward and Palm Beach counties. We prepare and submit the application, coordinate the architectural, structural and MEP drawings a project needs, respond to plan-review comments, and schedule the required inspections. The permit itself is issued by the government, not by us.

Who actually issues my building permit?

The building department with jurisdiction over your address. If the property sits inside an incorporated city, that city’s building official normally issues the permit. If it sits in an unincorporated area, the county does. In Miami-Dade, unincorporated properties are the ones whose folio number begins with 30.

Do I need a permit for a kitchen or bathroom remodel?

Almost always, because those projects touch electrical, plumbing or mechanical work, and none of that is exempt anywhere in Florida. Purely cosmetic work is the exception — West Palm Beach, for example, states that replacing flooring and painting in a house does not need a permit, while replacing flooring in an apartment or condo does. Your jurisdiction’s building department is the authority on your address.

How long does permit approval take?

It depends on the jurisdiction, the completeness of the drawings and the review queue, and only some jurisdictions publish a figure. Miami-Dade states that plan review may take between 24 hours and 10 business days. West Palm Beach states that a code-compliant residential remodel permit can be issued in roughly three weeks and a commercial remodel in roughly five. Both make the same point we do: comments restart the clock, and how fast they are answered is the part anyone can actually control.

The route

Project idea to permit approval

Not every project runs all eight stages. A like-for-like water-heater swap and a two-storey addition are both permitted work, but only one of them needs sealed structural drawings. The sequence below is the full route; we tell you which parts of it your project actually touches before you commit to anything.

01

Project scope

What is changing, what is staying, and whether structure, electrical, plumbing or mechanical are involved. This is what determines everything after it.

Elbaz + you
02

Drawings

Existing and proposed plans at the level of detail your jurisdiction requires — from a single-sheet layout to a full architectural set.

Design team
03

Engineering

Structural, and mechanical/electrical/plumbing, where the scope calls for it. Load-bearing changes and new construction normally do.

Engineer of record
04

Permit application

Filed in the jurisdiction’s portal under the licensed contractor’s name, with the drawings, product approvals and forms that application requires.

Elbaz
05

Plan review

The building department reviews the submission — often across several disciplines at once, such as structural, electrical, plumbing, zoning and fire.

Jurisdiction
06

Comments & corrections

Reviewers post comments. Drawings are revised and resubmitted. This loop is the single biggest variable in any permit timeline.

Elbaz + design team
07

Permit issued

The permit is issued and the permit card lists the inspections the job will need. Construction can legally begin.

Jurisdiction
08

Inspections

Called at the stages the permit card sets out, through to final inspection and, where applicable, a certificate of occupancy or completion.

Elbaz + inspector
Illustrative library photograph, not an Elbaz project: three people on a construction site reviewing a drawing spread across a board
Illustrative library photograph — not an Elbaz project.

Where projects actually stall

Almost never at step 04. The application itself is the easy part. Projects stall at step 02, when the drawings are not detailed enough for the jurisdiction to review, and at step 06, when comments come back and nobody owns the response.

That second loop is where weeks disappear. West Palm Beach says so in its own words: if the submitted documents are not code-compliant, plan-review comments are posted and the timeline is then affected by how long the customer takes to resubmit. The part anyone can control is the quality of the first submission and the speed of the answer — which is exactly the part we take on.

Responsibility

Who handles what

Five parties, and only one of them can issue you a permit. Knowing which is which is most of what makes this process calm rather than bewildering.

01

Homeowner

  • Project goals and priorities
  • Finish and fixture selections
  • Budget decisions
  • Signing the contract and applications that need an owner signature

02

Elbaz

  • Scope definition and constructability
  • Coordinating the design team
  • Preparing and filing the permit application
  • Answering plan-review comments
  • Building the work and calling inspections

03

Design team

  • Architectural drawings
  • Structural engineering where required
  • Mechanical, electrical and plumbing design
  • Sealed and signed documents

04

Jurisdiction

  • Reviews the submitted plans
  • Issues plan-review comments
  • Sets the fees
  • Issues — or refuses — the permit

05

Inspector

  • Attends at the required stages
  • Passes or fails each inspection
  • Signs off the final inspection
  • Works for the jurisdiction, not for the contractor

Scope

How complex is your project?

This ladder is how Elbaz plans a job — it is not a legal classification. What your project actually needs is set by your jurisdiction and by the specific scope, and the only authority on that is the building department for your address.

Cosmetic

Painting, and in a house, like-for-like flooring. Often no building permit — but the same work in a condo may well need one.

Light permitting

Small, contained changes with a single trade involved and no structural or layout change.

Moderate

Kitchens, bathrooms, window and door replacement, roof replacement. Multiple trades, product approvals, several inspections.

Complex

Structural remodeling — removing or altering walls that carry load, new openings, changes to the roof structure.

Major

Additions, ADUs and garage conversions, whole-home renovation. Zoning review as well as building review.

Full permit set

New construction. Architectural, structural and MEP drawings, site and civil work, and the longest review of anything on this list.

Jurisdiction

Who issues my permit?

This is the question that derails more South Florida projects than any other, and it has nothing to do with your mailing address. What matters is whether your property is inside an incorporated municipality or in the unincorporated part of the county.

Inside a city

If the property sits within an incorporated municipality, that city’s building department normally issues the permit and runs the inspections — not the county. Miami-Dade puts it plainly: the county has 35 municipalities, "each with its own building official overseeing permits and inspections."

Unincorporated county

If the property is in an unincorporated area, the county building department has jurisdiction. Miami-Dade publishes a clean test for this: the county handles buildings in unincorporated areas with a folio number that begins with 30. Broward’s Building Code Division covers unincorporated Broward and the cities it contracts with; Palm Beach County’s Permit Center processes applications for the unincorporated area.

35Municipalities in Miami-Dade County
31Municipalities in Broward County
39Municipalities in Palm Beach County

Broward’s figure is the commonly cited count of incorporated municipalities in the county; Miami-Dade’s 35 and Palm Beach’s 39 are stated on the counties’ own pages. Either way the point holds: most South Florida addresses are permitted by a city, not by a county.

Sometimes both

Being inside a city does not always mean the county is out of the picture. Miami-Dade publishes a "County Municipal Approval" route for projects inside municipalities that still need county review for water and sewer, impact fees, environmental resources (DERM), fire rescue, or the Florida Department of Health for septic tanks. In Broward, the ePermits OneStop platform exists precisely so that county approvals attached to a municipal permit can be handled online alongside it.

West Palm Beach is a city, not the county

This one catches people constantly. West Palm Beach is an incorporated municipality inside Palm Beach County, and it runs its own Development Services Building Division with its own portal, its own fees and its own inspectors. A property inside the city limits is permitted by the City of West Palm Beach — not by Palm Beach County’s Permit Center at 2300 N. Jog Road. They are two different authorities and they are not interchangeable.

Statewide · in effect since 1 July 2026

What Florida HB 803 changed

CS/CS/HB 803, "Building Permits and Inspections", was approved by the Governor on 6 May 2026 as Chapter 2026-63 and took effect on 1 July 2026. It is the most significant change to Florida residential permitting in years, and it is widely misunderstood.

The $7,500 exemption is real

Work on a single-family dwelling valued at under $7,500 can be exempted from the requirement to obtain a building permit.

But it is not automatic

The owner or the owner’s contractor must submit a written request with documentation of the nature and value of the work, and receive approval, before the work starts. West Palm Beach created a "Permit Exemption" application type and issues an Exemption Certificate when it approves one; Fort Lauderdale requires its own request form with a job cost estimate and states you must "receive written approval before starting work."

Most real remodeling is excluded

Structural, electrical, mechanical, plumbing and gas work are not eligible regardless of value. Fort Lauderdale also lists window replacements, AC units, commercial and multifamily property, condominiums and apartments, and homes in flood zones.

Flood hazard areas are out

Any work on a property located partly or entirely within a flood hazard area is excluded — which in South Florida is a great deal of property.

You cannot split a job

A project may not be divided into smaller projects to stay under the $7,500 threshold.

Zoning rules still apply

West Palm Beach still requires fence, pool-barrier and driveway permits, because those come from the City’s zoning code, which HB 803 does not amend.

What this means for a remodel

The practical effect for most homeowners is narrower than the headline suggests: it covers cosmetic, non-structural work and little else. If you are remodeling a kitchen or a bathroom, you are almost certainly still permitting it. Municipalities are implementing this differently, so check with the building department for your address.

01

Miami-Dade County

Building Permits in Miami-Dade

Miami-Dade is the largest and most procedurally demanding of the three, and it is also the one that publishes the most about how its process actually runs.

Authority
Department of Regulatory and Economic Resources (RER) — Building & Permits
Permitting & Inspection Center
Herbert S. Saffir Permitting and Inspection Center, 11805 SW 26 Street, Miami, FL 33175
Main phone
786-315-2000
Jurisdiction
Unincorporated Miami-Dade — folio numbers beginning 30. The county’s 35 municipalities each have their own building official.

How applications are submitted

The main route is the county’s Plan Status and Application Submittal Portal, where you file a new application, a rework against an existing number, a revision or shop drawing, a permit extension, a reissuance or a change of contractor. A submission returns a confirmation number — a UP# — and an email confirmation. Contractors can also use the separate e-Permitting system for permits that require no plan review at all, such as roofing, storm panels and accordion shutters, and electrical, mechanical or plumbing work that does not need review.

Who can hold the permit

Miami-Dade states it directly: building permits are issued in the name of the person performing the work, and only licensed contractors or Owner-Builders may obtain one. An Owner-Builder has to sign a form acknowledging what that responsibility means before the permit is issued. When Elbaz builds the project, the permit is in our name and the responsibility is ours.

Plan review, and the fee that gates it

Review is coordinated across disciplines at the Permitting and Inspection Center — building, electrical, roofing, mechanical, plumbing and structural, plus zoning, impact fees, public works, fire rescue, DERM and the Department of Health. The county states that plan review may take between 24 hours and 10 business days depending on permit type and complexity. One detail catches people out: plans are not reviewed until the required upfront fees are paid, so an unpaid application simply sits.

Comments, corrections and inspections

When reviewers raise comments, corrections go back through the portal with a contact sheet, and appointments with plan-review staff can be booked. Once the permit is issued, the permit card lists every inspection the job needs; requests must be made one business day before the date you want. Some inspections are conducted virtually over Microsoft Teams rather than in person.

Illustrative library photograph, not an Elbaz project: an architectural floor-plan line drawing showing room outlines and openings
Illustrative library photograph — not an Elbaz project.

On the numbers

The 24-hour-to-10-business-day figure is Miami-Dade’s published plan-review window, not a whole-permit timeline, and it does not include the time taken to answer comments.

Miami-Dade County · requirements

What a submission usually contains

Typical requirements may include the following. This is how Elbaz scopes a job before design starts — it is not a jurisdiction’s checklist, and no two projects submit exactly the same package. The building department for your address sets the actual requirements.

General planning categories — Miami-Dade projects
Project typeTypical plans / documentationPossible engineeringPermit complexity
Kitchen remodelFloor plan, plus electrical and plumbing layouts as applicableMEP where requiredLow–Medium
Bathroom remodelArchitectural, plus plumbing and electrical as applicableMEP where requiredLow–Medium
Interior remodelExisting and proposed plansStructural and/or MEP depending on scopeLow–Medium
Impact windows & doorsOpening schedule and product approval documentationStructural details where requiredLow–Medium
RoofingRoofing documents and product approvalsEngineering where applicableLow–Medium
AdditionFull architectural plansStructural and MEPHigh
ADU or garage conversionArchitectural, plus zoning reviewStructural and MEPHigh
New constructionFull permit set, plus site and civil documentationStructural and MEPVery high
Miami-Dade — what the county states about its own process
StageWhat Miami-Dade statesWhere it happens
ApplicationNew application, rework, revision/shop drawing, extension, reissuance or change of contractor. Returns a UP# and email confirmation.EPS submittal portal
No-plan-review permitsContractors may obtain roofing, storm panel, accordion shutter and certain electrical, mechanical and plumbing permits that require no plan review.e-Permitting system
FeesPlans are not reviewed until the required upfront fees are paid.e-Payment
Plan reviewMay take between 24 hours and 10 business days, depending on permit type and project complexity.Permitting & Inspection Center
CorrectionsCorrections are submitted with a contact sheet; appointments with plan review staff can be booked.EPS portal / MeetQ
InspectionsThe permit card lists required inspections. Requests must be made one business day before the date. Some inspections are conducted virtually.Inspection routes
02

Broward County

Building Permits in Broward

Broward works differently from Miami-Dade in one important way: for most addresses the county is not your permitting authority at all — your city is.

Authority
Broward County Building Code Division (Resilient Environment Department)
Office
2307 W. Broward Blvd., Suite 300, Fort Lauderdale, FL 33312
Main phone
954-765-4400 · Mon–Fri 8:00 AM–3:30 PM
Jurisdiction
Unincorporated Broward and the cities the division contracts with, including the Broward Municipal Services District and Fort Lauderdale-Hollywood International Airport.

Your city is usually the permitting authority

The Building Code Division describes its own remit as regulating construction "in unincorporated Broward County and cities we contract with." Everywhere else — which is most of Broward, including Fort Lauderdale, Hollywood, Pembroke Pines, Coral Springs, Davie and the rest — the municipality issues the permit through its own system. Fort Lauderdale runs LauderBuild; other cities run their own. The first question on any Broward job is therefore which city you are in.

ePermits OneStop, and why it exists

Broward’s distinctive mechanism is a shared platform. Because a municipal building permit often carries county-level approvals with it, Broward County and its municipalities built ePermits OneStop so those county approvals can be applied for and received online alongside the city permit, instead of requiring a separate trip to Government Center West in Plantation. It covers municipal building permits, associated county approvals, asbestos applications, transportation and environmental reviews, and Notice of Commencement filings.

What that means in practice

On a Broward remodel we are typically running two tracks at once: the city’s own submission and review, and any county approvals attached to it. Neither one alone is the permit. Coordinating the two — and knowing in advance which county reviews a given scope will trigger — is most of the work.

A note on availability

The Building Code Division’s site currently carries a notice that ePermits may be unavailable while the county upgrades its website. We check the live status before relying on any portal, and fall back to the division directly when we have to. Neither we nor anyone else can promise a government system will be up on a given day.

Illustrative library photograph, not an Elbaz project: two people at a counter reviewing a large-format drawing set together
Illustrative library photograph — not an Elbaz project.

On the numbers

Broward County does not publish a plan-review or inspection timeline on the pages referenced here, and municipal timelines vary by city, so this page does not quote one. Where a city publishes its own figure, that city is the source to trust.

Broward County · requirements

What a submission usually contains

Typical requirements may include the following. This is how Elbaz scopes a job before design starts — it is not a jurisdiction’s checklist, and no two projects submit exactly the same package. The building department for your address sets the actual requirements.

General planning categories — Broward projects
Project typeTypical plans / documentationPossible engineeringPermit complexity
Kitchen remodelFloor plan, plus electrical and plumbing layouts as applicableMEP where requiredLow–Medium
Bathroom remodelArchitectural, plus plumbing and electrical as applicableMEP where requiredLow–Medium
Interior remodelExisting and proposed plansStructural and/or MEP depending on scopeLow–Medium
Impact windows & doorsOpening schedule and product approval documentationStructural details where requiredLow–Medium
RoofingRoofing documents and product approvalsEngineering where applicableLow–Medium
AdditionFull architectural plansStructural and MEPHigh
ADU or garage conversionArchitectural, plus zoning reviewStructural and MEPHigh
New constructionFull permit set, plus site and civil documentationStructural and MEPVery high
Broward — who does what on a typical municipal job
ElementUsually handled byNotes
Building permitYour city’s building departmentMost Broward addresses are inside an incorporated municipality with its own system.
Unincorporated / BMSD addressesBroward County Building Code DivisionCovers unincorporated Broward and the cities the division contracts with.
Associated county approvalsBroward County, via ePermits OneStopApplied for online alongside the municipal permit rather than in person.
Asbestos applicationBroward County, via ePermits OneStopListed among the applications the platform handles.
Transportation & environmental reviewBroward County, via ePermits OneStopWhere a scope triggers them.
Notice of CommencementFiled through ePermits OneStopListed among the filings the platform handles.

Broward County · official tools

Go straight to the source

Every link below is an official government resource and opens in a new tab. These are the authoritative places to check current requirements, fees, status and forms — this page is a guide, they are the record.

Before you rely on any of these

Broward County’s Building Code Division currently notes that ePermits may be unavailable while its website is upgraded. Government systems go offline; neither we nor anyone else can promise otherwise.

03

Palm Beach County & West Palm Beach

Permits in Palm Beach County

Two authorities, one county, and they are routinely confused for each other. Palm Beach County permits the unincorporated area. The City of West Palm Beach permits properties inside its own limits.

County authority
Palm Beach County Planning, Zoning & Building (PZB) — Building Division
County office
2300 N. Jog Road, West Palm Beach, FL 33411 · Mon–Fri 8:00 AM–5:00 PM. South County: 345 S. Congress Ave, Delray Beach.
County phone
561-233-5000 (PZB) · 561-233-5100 (Building Division)
City authority
City of West Palm Beach Development Services — Building Division, City Hall, 401 Clematis Street · 561-805-6700 · ds@wpb.org

Palm Beach County — the unincorporated area

The county’s Permit Center processes permit applications for building construction in the unincorporated area, and runs everything through ePZB, its electronic Planning, Zoning and Building portal. ePZB handles plan-review tracking, permit status, inspection scheduling and history, and fee estimation for both building and impact fees. Field inspectors work Monday to Friday, 7:00 a.m. to 3:30 p.m. A Notice of Commencement filed with the county has to carry the property’s legal description, street address and tax folio (PCN) number, as Florida Statute 713.13 requires.

City of West Palm Beach — inside the city limits

The City runs its own Building Division through Civic Access, its Enterprise Permitting & Licensing portal, where you apply for permits, check status, pay fees, resubmit for plan review, download the permit card and approved plans, and schedule inspections. It also publishes a Research Tool that lets you check a proposed project against the zoning code and see which permits it will require — genuinely useful before you design anything.

West Palm Beach publishes real numbers

Unusually, the City states timelines and fees openly. If the submitted documents are code-compliant, a residential remodel permit can be issued in approximately three weeks and a commercial remodel permit in approximately five. If they are not, plan-review comments are posted and the timeline then depends on how quickly they are answered. On fees, the minimum combined plan review and permit fee is $105 for a project value up to $1,000, $130 up to $2,500, and $580 at a project value of $20,000 — excluding Fire Department and Zoning fees, which do not apply to every project.

And what happens if you skip it

The City is equally direct about unpermitted work: you will either have to permit the work or remove it, and a penalty fee of four times the regular permit fee applies. An unpermitted work case can go to a Special Magistrate, whose fines accrue daily and can be recorded as a lien — which is what makes a property difficult to sell or refinance years later. This is the single most expensive way to save money on a remodel.

Illustrative library photograph, not an Elbaz project: two hands pointing at a floor plan beside a scale rule and an orange hard hat
Illustrative library photograph — not an Elbaz project.

On the numbers

The three-week and five-week figures and the fee examples are the City of West Palm Beach’s own published statements about its own process, and are conditional on the submitted documents being code-compliant. They do not apply to Palm Beach County’s unincorporated area, or to any other city.

Palm Beach County & West Palm Beach · requirements

What a submission usually contains

Typical requirements may include the following. This is how Elbaz scopes a job before design starts — it is not a jurisdiction’s checklist, and no two projects submit exactly the same package. The building department for your address sets the actual requirements.

General planning categories — Palm Beach projects
Project typeTypical plans / documentationPossible engineeringPermit complexity
Kitchen remodelFloor plan, plus electrical and plumbing layouts as applicableMEP where requiredLow–Medium
Bathroom remodelArchitectural, plus plumbing and electrical as applicableMEP where requiredLow–Medium
Interior remodelExisting and proposed plansStructural and/or MEP depending on scopeLow–Medium
Impact windows & doorsOpening schedule and product approval documentationStructural details where requiredLow–Medium
RoofingRoofing documents and product approvalsEngineering where applicableLow–Medium
AdditionFull architectural plansStructural and MEPHigh
ADU or garage conversionArchitectural, plus zoning reviewStructural and MEPHigh
New constructionFull permit set, plus site and civil documentationStructural and MEPVery high
Palm Beach County vs. City of West Palm Beach
Palm Beach County (unincorporated)City of West Palm Beach
AuthorityPlanning, Zoning & Building — Building DivisionDevelopment Services — Building Division
PortalePZB, plus eField for inspectionsCivic Access (Enterprise Permitting & Licensing)
Office2300 N. Jog Road, West Palm Beach · South County office in Delray BeachCity Hall, 401 Clematis Street
Phone561-233-5000 (PZB) · 561-233-5100 (Building)561-805-6700 · ds@wpb.org
Published timelineNot stated on the pages referenced hereApprox. 3 weeks residential remodel, approx. 5 weeks commercial remodel, if documents are code-compliant
InspectionsField inspectors Mon–Fri, 7:00 a.m.–3:30 p.m., scheduled in ePZB/eField"Today’s Inspections" in Civic Access from 7:30 AM shows the primary inspector and a direct phone number
Fee estimatingBuilding and impact fee estimators inside ePZBFee Estimator inside Civic Access

Palm Beach County & West Palm Beach · official tools

Go straight to the source

Every link below is an official government resource and opens in a new tab. These are the authoritative places to check current requirements, fees, status and forms — this page is a guide, they are the record.

Before you rely on any of these

If your property is inside a Palm Beach County municipality other than West Palm Beach, start from the Property Appraiser’s municipal permit-department directory — that city, not the county, is your permitting authority.

Schedule a Consultation (754) 236-0675

Customer reviews

What clients said on Google.

4.8Based on 343 Google reviews

Asher was the best choice I have made. We love the outcome of the ADU . They showed up on time and did a great job, were friendly. No issues at all during the whole process. Very organized team . I would recommend them to everyone I know !

Robert Bryan

Great experience! The team was professional, efficient, and delivered high-quality work on time. They communicated clearly throughout the project and exceeded our expectations. Highly recommend for any construction needs!

Andrew

If you are planning to remodel your kitchen or bathroom or do any other construction project, call Sean from Elbaz Construction . He has a lot of experience and will recommend the best options/ suggestions to your project. He did high quality job !

Kameron Allison

Thank you Ashley ! We love the new bathrooms. Good with communication and very clear with explanations . I will definitely use them again in the future

Andrew Tyupa

Asher has a lot of experience . We replaced our windows to energy efficient windows. He got down to business right away and did high quality work. His team is very professional! Thanks again

jessica berliner

I give them a five star rating not only for their excellent roofing skills and timelines, but also for their competitive pricing and the honesty and professionalism of the team !! We are very pleased with the outcome

Zachary Gugliotta

These are genuine Google reviews of Elbaz Construction, reproduced as written. None of them is about permitting specifically; they are here because coordination, communication and running an organised process are exactly what a permitted project depends on.

Permit questions

Straight answers.

Requirements vary by address and by scope. If you want a real answer for yours, call (754) 236-0675.

Yes. Elbaz Construction is a licensed Florida general contractor, licence CBC1265280, and pulls permits in its own name for the work it builds across Miami-Dade, Broward and Palm Beach counties. We define the scope, coordinate the drawings and engineering the project needs, file the application, answer plan-review comments and call the inspections. The permit is issued by the government building department, not by us, and we cannot guarantee that any application will be approved.

In nearly every case, yes. A kitchen remodel normally involves electrical and plumbing work, and often cabinetry changes that move both — none of which is exempt anywhere in Florida, including under HB 803. If your address is in unincorporated Miami-Dade the county issues the permit; if it is inside one of the county’s 35 municipalities, that city’s building official does. The exact drawings required depend on how much of the layout is changing.

Almost always. Bathroom work touches plumbing and usually electrical, and where the shower or tub is being reconfigured it involves waterproofing that has to be inspected. A like-for-like cosmetic refresh with no plumbing or electrical change is the only realistic exception, and even that varies — West Palm Beach states that replacing flooring in an apartment or condo does require a permit, while in a house it does not.

Yes. West Palm Beach states it plainly: a permit is required for replacing windows and doors, the products must meet the wind loads experienced locally, and they must be installed in accordance with the manufacturer’s product approval documents. Miami-Dade lists windows and doors among the work homeowners need permits for. Fort Lauderdale specifically excludes window replacement from the HB 803 exemption. Product approval documentation is part of the submission, which is why we confirm approvals before anything is ordered.

Yes — roof replacement is permitted work throughout South Florida. In Miami-Dade, roofing is one of the categories a contractor can obtain through the county’s e-Permitting system when the permit requires no plan review. Roofing carries its own inspection sequence, and West Palm Beach publishes guidance on scheduling a preliminary inspection before starting work so the inspector can set expectations for what will be required.

An addition normally needs a full architectural set, plus structural engineering, plus mechanical, electrical and plumbing design — and it triggers zoning review as well as building review, because you are changing the footprint. The precise set is determined by the jurisdiction and the scope. We establish that at the scoping stage rather than after drawings are underway, because redrawing to a requirement nobody checked is the most avoidable cost in this process.

A full permit set: architectural drawings, structural engineering, mechanical, electrical and plumbing design, and site and civil documentation. In Miami-Dade, review is coordinated across building, electrical, roofing, mechanical, plumbing and structural disciplines as well as zoning, impact fees, public works, fire rescue, DERM and the Department of Health. It is the longest review of any residential project type.

No, and assuming it does is expensive. A single-trade replacement may need very little. A kitchen that keeps its layout needs less than one that moves the plumbing. Structural engineering is triggered by what you are doing to the structure — removing or altering load-bearing walls, forming new openings, changing the roof structure — not by the size of the budget. We scope which disciplines your project actually requires before commissioning any of them.

Applications are filed through the county’s Plan Status and Application Submittal Portal, which returns a confirmation number (a UP#) and an email confirmation. Plans are not reviewed until the required upfront fees are paid. Review is coordinated across multiple disciplines at the Permitting and Inspection Center, and the county states it may take between 24 hours and 10 business days depending on permit type and complexity. Corrections go back through the portal. Once issued, the permit card lists the required inspections, which must be requested one business day in advance.

For most Broward addresses, your city issues the permit through its own system — Broward County’s Building Code Division has jurisdiction over unincorporated Broward and the cities it contracts with. Where a municipal permit carries county-level approvals with it, those are handled through ePermits OneStop, a shared platform built by the county and its municipalities so approvals can be applied for online alongside the city permit rather than in person at Government Center West.

Palm Beach County’s Permit Center processes applications for the unincorporated area through ePZB, its electronic Planning, Zoning and Building portal, which handles plan-review tracking, permit status, inspection scheduling and fee estimation. County field inspectors work Monday to Friday, 7:00 a.m. to 3:30 p.m. If your property is inside one of the county’s 39 municipalities, that municipality permits it instead.

The City of West Palm Beach, not Palm Beach County. West Palm Beach is an incorporated municipality inside the county and runs its own Development Services Building Division from City Hall at 401 Clematis Street, with its own Civic Access portal, its own fee schedule and its own inspectors. Palm Beach County’s Permit Center at 2300 N. Jog Road handles the unincorporated area. Confusing the two is the most common jurisdiction mistake in the county.

It varies by jurisdiction, by how complete the drawings are, and by the review queue — and only some jurisdictions publish a figure at all. Miami-Dade states plan review may take between 24 hours and 10 business days. West Palm Beach states a code-compliant residential remodel permit can be issued in approximately three weeks and a commercial remodel in approximately five, and adds that if documents are not code-compliant the timeline then depends on how quickly comments are answered. No contractor controls a government review queue, and anyone promising a date is guessing.

Comments are the normal outcome of a first review, not a failure. The reviewer posts what needs to change, the design team revises the affected sheets, and the set is resubmitted — in Miami-Dade as a rework through the portal with a contact sheet. Each round takes time, which is why the quality of the initial submission matters more than anything else in the timeline. This loop is the single largest variable in any permit schedule.

We do, on the projects we build. The permit card issued with the permit lists which inspections the job requires. Miami-Dade requires requests one business day before the desired date and conducts some inspections virtually over Microsoft Teams. Palm Beach County’s field inspectors work 7:00 a.m. to 3:30 p.m., Monday to Friday. West Palm Beach publishes the primary inspector and a direct phone number in its Civic Access portal from 7:30 AM on the day. The inspector works for the jurisdiction, not for us.

We coordinate them. Architectural drawings, structural engineering and MEP design are produced by the licensed design professionals a project requires, and we manage that process — briefing the team on the real construction scope, checking the set against what the jurisdiction will look for, assembling the submission, and handling the comments that come back. If you already have drawings, we will review them against the scope and tell you honestly whether they are ready to file.

Do you already have plans or drawings?
Has a permit already been started?
Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale. Submitting this form does not start a permit application.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Plans. Permits. Construction.

One team from concept to completion.

Elbaz Construction coordinates the planning, the documentation, the permit process and the construction itself — so the drawings that get approved are the drawings the build team actually works from. Across Miami-Dade, Broward and Palm Beach.

Call (754) 236-0675 · Sun–Fri 7am–7pm

Important:

Permit requirements vary by jurisdiction, by property and by scope of work. Nothing on this page is a determination about your project.

Building permits are issued by government building departments — the county or the municipality with jurisdiction over your address. Elbaz Construction is a licensed general contractor and is not a government permitting authority. We cannot guarantee that any permit application will be approved, and we do not control government review times.

Timelines depend on project complexity, the jurisdiction, the completeness of the submitted documents, the plan-review comments raised and the agency’s own workload. Where this page quotes a timeline or a fee, it is quoting that jurisdiction’s own published statement, with the conditions that jurisdiction attached to it.

Municipal rules frequently differ from county rules, and municipalities are implementing Florida HB 803 differently from one another.

The official government portals and building departments linked from this page are the authoritative source for current requirements, fees and forms. Information here was compiled from those sources on 13 August 2026 and may since have changed.