How Long Does a Bathroom Remodel Take in South Florida?

The two clocks behind every bathroom remodel: the permit review, now limited by Florida’s 2026 deadlines, and the build, with its inspection hold points.

5 dayspermit decision, small single-family jobs
30 daysmost other home permits
15 minminimum shower liner flood test
By Elbaz ConstructionUpdated September 25, 20269 min readSources: Florida Statutes · Florida Building Code · county and city building departments

Bathroom remodel timeline

The short answer

A bathroom remodel runs on two clocks. The first is the permit: since July 1, 2026, Florida law gives the building department 5 business days to decide a complete application for work under $15,000 on an existing single-family home, and 30 business days for most other home permits. The second is the build, a fixed sequence of trades with inspection hold points: nothing gets covered until the inspector approves it. The avoidable delays come from decisions made late, such as fixtures ordered after demolition or a layout changed after the permit.

Decide first

Layout, fixtures and tile chosen and ordered before demolition keep the trades moving.

Permit clock

The legal clock starts only when the application is complete and sufficient.

Hold points

Rough-in, shower liner and final inspections must pass before work continues.

Hidden conditions

Rot, leaks or old wiring found behind the walls add a fix and often a revision.

Before any demolition

Clock one: how long the permit can take

Most bathroom remodels need a permit, because they move or replace plumbing, wiring or ventilation (Florida Building Code, section 105.1). Florida then limits how long the building department may take. Section 553.792, Florida Statutes, as amended by HB 803 (chapter 2026-63, in force since July 1, 2026), sets these maximums once an application is “complete and sufficient”:

Four details decide whether those numbers help you:

  • The clock starts at “complete”. The department has 5 business days to tell you what is missing. If it says nothing, the application is treated as complete. Missing drawings or product approvals restart the wait.
  • Corrections have their own clock. After you resubmit corrected plans, the department has 10 business days to approve or deny them. Some cities also set a deadline for you: the City of Miami requires corrections to rejection comments within 10 business days, or the application is denied and must be resubmitted with fees.
  • A missed deadline costs the department, not you. The permit fee drops by 10% for each business day the department is late, unless both sides agree in writing to an extension. You may waive the timeframes in writing, but the law says the department cannot make a waiver a condition of reviewing your application.
  • Private providers are an option. Section 553.791 lets the owner use a licensed private provider for plan review, inspections or both, with separate statutory deadlines for the building official.

These are legal maximums, not predictions: a department can be faster. What you control is the quality of the application. A complete package with drawings, fixture and product details and the right trade permits is the fastest one. Our residential permit service and plan-review corrections exist for exactly that step.

Three questions

Which permit path your bathroom follows

Not every bathroom project follows the same path. HB 803 also added an exemption: the owner of a single-family dwelling may ask, in writing, to skip the permit for work valued under $7,500. It never covers electrical, plumbing, structural, mechanical or gas work, or a property in a flood hazard area, and splitting a project to get under the limit is not allowed. Fort Lauderdale’s guide adds that condos and multifamily buildings are not included. So the exemption fits cosmetic work only, such as new paint or a like-for-like vanity, and the building official still decides.

Which permit path a bathroom remodel follows in FloridaQuestion 1: does the work touch plumbing, electrical, gas, ventilation or structure? If yes, go to question 2: is it an existing single-family home with work valued under $15,000? If yes, the building department must decide within 5 business days of a complete application; if no, within 30 business days, or 60 for a structure of 7,500 square feet or more. If the answer to question 1 is no, question 3: single-family, under $7,500 and outside a flood hazard area? If yes, the owner may request a written exemption; if no, a permit is usually needed.QUESTION 1Does the work touch plumbing,electrical, gas, ventilationor structure?QUESTION 2Existing single-family homeand work valuedunder $15,000?DECISION DUE WITHIN5 business daysof a complete applicationQUESTION 3Single-family, under $7,500and outside a floodhazard area?YOU MAY ASK FORa written exemptionThe building official decidesDECISION DUE WITHIN30 business days60 if the structure is7,500 sq ft or moreYESYESNOYESNO: usuallya permitNOCondo units also need association approval, and the $7,500 exemption does not apply to them.Which permit path a bathroom remodel follows, as three questionsQUESTION 1Touches plumbing, electrical, gas,ventilation or structure?YES go to question 2NO go to question 3QUESTION 2Existing single-family home,work under $15,000?YES decision within 5 business daysNO within 30 (60 if 7,500 sq ft+)QUESTION 3Single-family, under $7,500,outside a flood hazard area?YES ask for a written exemptionNO usually a permit: question 2Condo units: association approval as well;the $7,500 exemption does not apply.
Simplified decision path under sections 553.79(1)(g) and 553.792, Florida Statutes (from July 1, 2026). Local exemption lists also cover some like-for-like work, such as replacing a toilet or sink in the same place; ask your building department.

Where the permit comes from depends on the address, not the county name. Each city in Miami-Dade, and most cities in Broward and Palm Beach, run their own building department. The county pages for Miami-Dade, Broward and Palm Beach and our three-county permit guide explain who handles what.

On site

Clock two: the build, and where it has to stop

Once the permit is issued, a full bathroom remodel runs in a fixed order, because each trade covers the work of the one before it. The order matters more than any single task: the schedule slips when a step has to wait for an inspection, a part or a decision.

The order of work in a permitted bathroom remodelSeven steps from left to right: demolition, rough-in, rough inspection, closing the walls and waterproofing, the shower liner test where a liner is used, tile and fixtures, and the final inspection. Steps 3, 5 and 7 are hold points: work stops until they pass.1DEMOLITIONStrip to studs2ROUGH-INPipes, wiring, fanHOLD POINT3ROUGHINSPECTIONInspector mustapprove first4CLOSE-INWaterproofingHOLD POINT5LINERTEST2 in. of water,15 min minimum6TILE ANDFIXTURESHOLD POINT7FINALINSPECTIONInspector mustapprove firstNothing at a hold point gets covered until it passes. A failed inspectionmeans a fix and a new inspection request, not the next trade.The order of work in a permitted bathroom remodel, in seven steps1DEMOLITIONStrip to studs2ROUGH-INPipes, wiring, fan3ROUGH INSPECTIONHOLD POINT: must pass first4CLOSE-INWaterproofing5LINER TESTHOLD POINT: 2 in. water, 15 min6TILE AND FIXTURESThen the glass enclosure7FINAL INSPECTIONHOLD POINT: must pass firstNothing at a hold point is covereduntil the inspector approves it.
The usual order of a permitted bathroom remodel. Steps 3, 5 and 7 are hold points; step 5 applies where the shower floor is made watertight with a liner, and the exact inspections depend on the permits issued.
Bathroom stripped back during demolition, with the wall board removed, supply pipework exposed and debris still on the floor
Mid-demolition on an Elbaz Construction bathroom remodel: wallboard stripped, supply lines exposed, debris on protective paper.
Shower floor tiled in pale hexagonal mosaic with a square centre drain and a matt black trim, seen from the opening
A finished shower floor from an Elbaz Construction remodel: white hexagonal mosaic, a square black drain and grey plank-format wall tile.
  • Demolition shows what the walls and floor hide. This is where rot, old leaks or outdated wiring appear, and where a fixed schedule can change.
  • Rough-in sets the new supply and drain lines, circuits, lighting boxes and the exhaust fan in their final positions. Moving a toilet or a shower drain is the slowest version of this step.
  • Rough inspection. Miami-Dade County’s building department states it plainly: “Inspections are required prior to covering any part of the construction.” The County inspects Monday to Friday, 8 a.m. to 3:30 p.m., and inspections are requested one business day ahead, with the approved plans and permit card on site. Beyond the first inspection and one follow-up, each extra inspection carries a fee.
  • Walls closed and waterproofed. Backer board goes up and the shower is waterproofed.
  • Shower liner test. Where the shower floor is made watertight with a liner, the Florida Building Code, Plumbing (section 312.9) requires a flood test: the drain plugged, at least 2 inches of water at the threshold, held for at least 15 minutes with no sign of leakage. Tile goes on only after it passes.
  • Tile, fixtures and glass. Tile, then the vanity, toilet, valves and trim, lighting and, last, the glass enclosure, which is usually measured after the tile is finished.
  • Final inspection closes the permit. Until then, the job is not finished on paper.

Planning

What keeps a schedule, and what stretches it

Most delays are not about how fast anyone works. They come from a decision or a discovery arriving after the step that needed it.

Settled before demolition: keeps the schedule

  • Final layout, with drains and valves located on the drawings
  • Vanity, fixtures, valves and tile chosen and ordered
  • Product approvals and details in the permit package
  • Association or HOA approval requested at the same time as the permit
  • Access, parking and work hours agreed

Arriving after demolition: stretches it

  • Hidden damage behind walls or under the floor
  • A layout change after the permit, which can mean revised drawings
  • A special-order item that has not arrived when the trade is ready
  • A failed inspection and the fix before the re-inspection
  • Choices left open until the tile setter or plumber asks
Bathroom with the walk-in shower on the left and a timber vanity and basin alongside
A finished Elbaz Construction bathroom: frameless glass shower with a lit ledge niche, brass fittings and a floating wood vanity.

Special cases

Condos, HOAs and flood zones

  • Condo units need the association’s approval under the building’s documents as well as the permit, and the $7,500 exemption does not apply. Building rules on work hours, elevators and noise shape the schedule too. Our guide to condo renovation approvals and permits covers the sequence.
  • Homes in an HOA. Since July 1, 2026, an HOA or its architectural committee may not require a building permit before it reviews your project (section 720.3035(1)(c), added by HB 803). HOA review and permit review can therefore run at the same time. See HOA and historic approvals.
  • Flood zones. The under-$7,500 exemption excludes any property in a flood hazard area. If the bathroom is part of a larger renovation, check the FEMA 50% rule before the scope is fixed, because it can change what the whole project must meet.
Bathroom with a navy hexagonal tiled shower behind a framed glass screen, brass fittings, a recessed niche and a white vanity
Navy hexagonal shower tile, brass fittings and a mosaic-lined niche behind a glass screen, from an Elbaz Construction bathroom.
Bathroom remodel by Elbaz Construction in South Florida: large-format white wall tile, matt black brassware, a blue shaker vanity with a marble top and a patterned floor
A navy shaker double vanity with a marble-look top and large-format white wall tile, from an Elbaz Construction remodel.

Interactive checklist

Before demolition day: a checklist

0 of 8 done

Our process

How we plan a bathroom remodel

On our bathroom remodels, from a full bathroom remodel to a walk-in shower conversion or a tub-to-shower conversion, the layout, selections and permit package are settled before demolition, so the trades are not waiting on decisions. On a design-build project, the drawings the building department reviews are the drawings we build.

We do not publish a standard duration, because the permit path, the building and what is behind the walls differ on every job. We give you a schedule for your bathroom after we have seen it. Send us your plans or photos and we will tell you which permits apply and what the sequence looks like.

Our work

Bathrooms we have built

Real Elbaz Construction projects. Photos show the work only; none is presented as a particular home or location. Tap a photo to enlarge.

Google reviews

What clients said on Google.

4.8348 Google reviews (checked Sep 2026)

Asher was the best choice I have made. We love the outcome of the ADU . They showed up on time and did a great job, were friendly. No issues at all during the whole process. Very organized team . I would recommend them to everyone I know !

Robert Bryan

Great experience! The team was professional, efficient, and delivered high-quality work on time. They communicated clearly throughout the project and exceeded our expectations. Highly recommend for any construction needs!

Andrew

If you are planning to remodel your kitchen or bathroom or do any other construction project, call Sean from Elbaz Construction . He has a lot of experience and will recommend the best options/ suggestions to your project. He did high quality job !

Kameron Allison

Thank you Ashley ! We love the new bathrooms. Good with communication and very clear with explanations . I will definitely use them again in the future

Andrew Tyupa

Asher has a lot of experience . We replaced our windows to energy efficient windows. He got down to business right away and did high quality work. His team is very professional! Thanks again

jessica berliner

I give them a five star rating not only for their excellent roofing skills and timelines, but also for their competitive pricing and the honesty and professionalism of the team !! We are very pleased with the outcome

Zachary Gugliotta

Genuine Google reviews of Elbaz Construction, reproduced as written. They describe general work with us, not the specific topic of this article. Read all reviews on Google.

Questions

Quick answers on bathroom timelines

Rules vary by address and scope. For your property, call 754-236-0675.

It depends on two things: the permit and the build. Since July 1, 2026, Florida law gives the building department 5 business days to decide a complete application for work under $15,000 on an existing single-family home, and 30 business days for most other home permits. On site, the work follows a fixed sequence with inspection hold points. We give a schedule for your bathroom after seeing it, rather than a standard figure.

Under section 553.792, Florida Statutes, the department must tell you within 5 business days if the application is incomplete. It then has 5 business days to decide a complete application for work under $15,000 on an existing single-family home, 30 business days for home permits where the structure is under 7,500 square feet, and 60 business days for larger structures. Corrected plans get a 10-business-day review.

Only for cosmetic work. The HB 803 exemption lets the owner of a single-family dwelling request, in writing, an exemption for work under $7,500, but it never covers electrical, plumbing, structural, mechanical or gas work, or a property in a flood hazard area. Condos are not included. Most bathroom remodels touch plumbing or wiring, so they still need a permit.

Because tile covers the plumbing, wiring and waterproofing the inspector has to see. Miami-Dade County states that inspections are required before any part of the construction is covered. Where the shower floor uses a liner, the Florida Building Code also requires a flood test of at least 2 inches of water held for 15 minutes before tiling.

Often, because it needs two approvals: the association’s, under the building’s documents, and the building permit. Building rules on work hours, elevators and deliveries also shape the schedule. The under-$7,500 permit exemption does not apply to condos.

Preferred contact method

We use your details only to respond to this enquiry. No lists, no resale.

Thanks — that came through.

Your details are with the Elbaz Construction team and we will come back to you, usually the same or next working day. If it is urgent, call (754) 236-0675.

Sources

Where these facts come from

  1. Section 553.792, Florida Statutes: building permit application deadlines — (1)(a), (c), (e), (g)
  2. CS/CS/HB 803 (2026), chapter 2026-63, Laws of Florida — enrolled text: s. 553.792 amendments, s. 553.79(1)(g), s. 720.3035(1)(c); effective July 1, 2026
  3. Section 553.791, Florida Statutes: alternative plans review and inspection (private providers)
  4. City of Miami: new permitting rules per section 553.792
  5. Miami-Dade County: building inspections
  6. Florida Building Code, Plumbing, 8th edition (2023), section 312.9 shower liner test
  7. Florida Building Code, Building, 8th edition (2023), section 105.1
  8. City of Fort Lauderdale: HB 803 permit exemption guide

General information about Florida permit law and building code requirements as of September 2026, not legal advice. Deadlines are business days and apply to complete applications; your building department and the permits issued decide how they apply to your project.